Energy · Co. Dublin

30 MW capacity battery storage facility within a secured compound…, Dublin 8, Co. Dublin

Granted 13 Dec 2019 (final grant issued 28 Jan 2020)

We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 8 by email

Key facts

  • Planning application 4282/19 at Dublin 8, Co. Dublin: 30 MW capacity battery storage facility within a secured compound…
  • It was received by Dublin City Council on 23 Oct 2019.
  • Status: Granted 13 Dec 2019 (final grant issued 28 Jan 2020).

Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register

More planning applications in Dublin 8 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 13 Dec 2019.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

30 MW capacity battery storage facility within a secured compound…

The development will consist of a c. 30 MW capacity battery storage facility within a secured compound and will – subject to detailed design, commercial and technical considerations, include the following elements: (a) a control building (c. 279 sq.m., c. 4.7m high); (b) plant and equipment comprising: (1) up to 34 No. battery container units (c. 30 sq. m. and up to c. 4.7m high) with roof mounted HVACs; (2) up to 17 No. battery unit transformers on concrete plinths (c. 10.6 sq. m. and c. 4m high); (3) up to 17 No. inverter units (c. 30 sq. m. and c. 3 m high); (4) a bunded transformer (c. 66 sq. m. and c. 6 m high) with firewall on one side; (5) a bunded house transformer (c. 20 sq. m. and c. 3 m high) surrounded on three sides by a 3m high firewall; (6) VAR support system on a concrete plinth (c. 24 sq. m. and c. 3.4 m high); (7) cable trays and associated service connections; (8) other ancillary electrical plant; (9) up to 5 No. lightning masts (c. 20 m high); (10) a c. 18 m high SCADA Pole; (11) pole mounted security cameras (c. 8.3 m high); (c) c. 2.6 m high palisade fencing and gates; and (d) ancillary site clearance and developments works including provision of areas of hardstanding, internal access roads, and connections to site services networks. Primary access will be via the existing access location from Kylemore Way Road, to the north of the site. Secondary access, if required in exceptional circumstances, will be via an existing internal access to the east between the development site and the abutting ESB owned 110 kV and 220 kV substation compound. Planning permission is being sought for a duration of 10 years.

Location
Dublin 8, Co. Dublin Map
Planning reference
4282/19

Numbers and dates

Project type
Energy
Received
23 Oct 2019
Decision to grant
13 Dec 2019
Final grant
28 Jan 2020
Site start notified
28 Jun 2021

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 4282/19.Search the register

How we know this

From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 28 Jun 2021Notice filed · Installation of a new steel control unit container to house electrical equipment in a...View the site start
  2. Completion certificate recordedRecorded in Jun 2021 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 8

Get alerts for Dublin 8Free. We email you when new applications appear.

Free email alerts

Get new Dublin 8 projects by email

New applications, decisions and site starts in Dublin 8, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options