Commercial new build · Co. Dublin

Development within the existing Diageo brewery production facility, Dublin 8, Co. Dublin

Granted 22 Jan 2020 (final grant issued 3 Mar 2020)

We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 8 by email

Key facts

  • Planning application 4530/19 at Dublin 8, Co. Dublin: Development within the existing Diageo brewery production facility.
  • It was received by Dublin City Council on 25 Nov 2019.
  • Status: Granted 22 Jan 2020 (final grant issued 3 Mar 2020).

Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register

More planning applications in Dublin 8 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 22 Jan 2020.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Development within the existing Diageo brewery production facility

Planning permission for development within the existing Diageo brewery production facility at St. James's Gate, at a site located within the south-west corner of the St. James's Gate brewery lands bound by James Street to the south, Watling Street to the east, Steeven's Lane to the west and Victoria Quay to the north, Dublin 8. The proposed development will consist of: (1) The construction of a forklift building (GFA 236sq.m) (c.14.8m in height), with a return to the north and a metal canopy projecting from a section of the west elevation (+13.647m). The building will comprise of: a work area and gantry; office; breakroom; and storage area. The building will be accessible via: a double height roller shutter door on the west elevation; a single height roller shutter door on the north elevation; and standard pedestrian doors on the west, east and south elevations. Windows will be positioned on the north and west facades. An access ramp will also be installed on the north elevation. A fire escape cage ladder will be located on the southwest corner of the building. The building will have an aluminium clad facade, metal flashing at parapet level and roof lights. A pedestrian barrier will also be erected to the immediate west of the building for safety purposes. (2) The construction of a new canopy structure (GFA 1,070sq.m) (c.8.9m in height) made up of steel columns and trusses and a metal panel deck roof. The canopy will be open on each elevation. The fire escape ladder proposed as part of the forklift building will also connect to the canopy structure at roof level on the north elevation. (3) The construction of an oil containment building (GFA 21.8sq.m) (c.2.9m in height) with a blockwork facade and metal flashing at parapet level. The structure will have a flat roof and will be erected on a concrete plate. The structure will have four sets of welded wire mesh gates on the north elevation. (4) The construction of a hot works unit (GFA 28.7sq.m) (c.4.3m in height) with a metal clad facade and a metal pitched roof. The structure will be erected on a concrete plate. The hot works unit will be accessible via a roller shutter door on the north elevation and a standard pedestrian door on the west elevation. (5) All associated site development works on a site of c.0.24ha. The proposed development is located within a site which has an approved IE (Industrial Emissions) Licence (Ref. No. P0301-04).

Location
Dublin 8, Co. Dublin Map
Planning reference
4530/19

Numbers and dates

Floor area
1,356 m²
Project type
Commercial new build
Received
25 Nov 2019
Decision to grant
22 Jan 2020
Final grant
3 Mar 2020
Site start notified
17 Nov 2021

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work packages named so far

  • Roads and site development worksNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 4530/19.Search the register

How we know this

From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 17 Nov 2021Notice filed · The development will consist of the construction of a fork lift building (FLT Building)...View the site start
  2. Completion certificate recordedRecorded in Nov 2021 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 8

Get alerts for Dublin 8Free. We email you when new applications appear.

Free email alerts

Get new Dublin 8 projects by email

New applications, decisions and site starts in Dublin 8, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options