Mixed use · Co. Dublin

site at Newmarket, Brabazon Place, Brabazon Row and St. Luke's Avenue, Dublin 8

Granted 14 Sep 2020 (final grant issued 28 Oct 2020)

We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 8 by email

Key facts

  • Planning application 4743/19 at Site At Newmarket, Brabazon Place, Brabazon Row and St. Luke's Avenue, Dublin 8: ~2 homes.
  • It was received by Dublin City Council on 18 Dec 2019.
  • Status: Granted 14 Sep 2020 (final grant issued 28 Oct 2020).

Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register

More planning applications in Dublin 8 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 14 Sep 2020.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

~2 homes

The proposed development (6,448 m² gross floor area) will consist of a hotel (6,275 m²) comprising 151 bedrooms with all associated ancillary accommodation with access from Brabazon Lane and including public bar / restaurant, reception area, toilets and back-of-house areas at ground floor with access and external seating areas onto Newmarket; 2no. independent units on Newmarket comprising a café/restaurant (100 m²) and a retail unit (73 m²). The proposed development includes a new public routeway through the site from Newmarket to St. Luke’s Avenue. The building ranges from 6 storeys (including set back level) to Newmarket stepping to 8 storeys (including set-back level) on Brabazon Lane and includes a basement/lower ground floor level accessed from the new internal street. Permission is also sought for signage, hard and soft landscaping and all ancillary and associated site development works. The demolition of all existing buildings on the overall site known as the IDA Ireland Small Business Centre at Newmarket Industrial Estate has been approved and will be carried out pursuant to Reg Ref: 3323/17 (Bord Ref: ABP 300431-17). The remainder of the overall site bounded by Newmarket, Newmarket Street Brabazon Street and St. Luke’s Avenue will be subject to a separate planning application for a Strategic Housing Development (SHD) to An Bord Pleanála.

Location
Dublin 8, Co. Dublin Map
Planning reference
4743/19

Numbers and dates

Homes
~2estimated from the application
Floor area
151 m²
Estimated construction value
€260k to €340kOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Mixed use
Received
18 Dec 2019
Decision to grant
14 Sep 2020
Final grant
28 Oct 2020
Site start notified
17 May 2021

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work packages named so far

  • Roads and site development worksNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 4743/19.Search the register

How we know this

From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 17 May 2021Notice filed · phase 1 · The works provide for the construction of the lower ground floor level of the hotel...View the site start
  2. 10 Aug 2021Notice filed · phase 2 · The works provide for the construction of 8 new levels of a Hotel development at...View the site start
  3. Completion certificate recordedRecorded in May 2021 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
  4. Partial completion certificate recordedRecorded in Aug 2021 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 8

Get alerts for Dublin 8Free. We email you when new applications appear.

Free email alerts

Get new Dublin 8 projects by email

New applications, decisions and site starts in Dublin 8, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options