- Planning application 5059/23 at The Headline Bar, Junction of 57 Clanbrassil Street Lower & South Circular Road, Dublin 8, D08HC79: Change of use of first and second floors of existing licenced…
- It was received by Dublin City Council on 22 Dec 2023.
- Status: Granted 8 May 2024 (final grant issued 10 Jun 2024).
Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 8 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 8 May 2024.
Search the Dublin City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Change of use of first and second floors of existing licenced…
Change of use of first and second floors of existing licenced premises from existing bar/lounge area (at first floor) and existing storage rooms & ancillary accommodation (at second floor) to new guest accommodation to provide 7 no. guest bedrooms with ensuite bathrooms at first floor & 6 no. guest bedrooms with ensuite bathrooms at second floor (total 13 guest bedrooms) & ancillary storage accommodation. To include material alterations to facilitate works inc. new accommodation/escape stairs, remodelled entrance lobby at ground floor, and associated internal layout changes & external alterations, inc. alterations to fenestration, alterations to roof, removal of redundant services & chimneys etc. as indicated on dwgs to facilitate same, at "The Headline Bar", located at the junction of 57 Clanbrassil Street Lower & South Circular Road, Dublin 8, D08 HC79.
- Location
- Dublin 8, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- 5059/23
Numbers and dates
- Project type
- Commercial fit-out
- Received
- 22 Dec 2023
- Decision to grant
- 8 May 2024
- Final grant
- 10 Jun 2024
- Site start notified
- 17 Sep 2024
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 5059/23.Search the register
How we know this
From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 17 Sep 2024Notice filed · The proposed works involve the change of use of the top two floors and the refurbishment...View the site start
- Completion certificate recordedRecorded in Sep 2024 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.