Planning record · Co. Dublin
132 Barton Road East, Dublin 14, D14 W893
Granted 14 Sep 2022 (final grant issued 20 Oct 2022)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 14 by email
Key facts
- Planning application D22A/0542 at 132 Barton Road East, Dublin 14, D14 W893: New raised roof to existing side extension.
- It was received by Dun Laoghaire Rathdown County Council on 25 Jul 2022.
- Status: Granted 14 Sep 2022 (final grant issued 20 Oct 2022).
- Work was due to start on 26 Oct 2023, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Dun Laoghaire Rathdown County Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 14 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 14 Sep 2022.
Search the Dun Laoghaire Rathdown planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
New raised roof to existing side extension
Planning permission is sought for new raised roof to existing side extension
- Location
- Dublin 14, Co. Dublin Map
- Planning reference
- D22A/0542
Numbers and dates
- Project type
- Planning record
- Received
- 25 Jul 2022
- Decision to grant
- 14 Sep 2022
- Final grant
- 20 Oct 2022
- Site start notified
- 26 Oct 2023
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference D22A/0542.Search the register
How we know this
From the Dun Laoghaire Rathdown County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 26 Oct 2023Notice filed · Construction of single storey rear extension, new roof to existing rear extension and...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.