One-off house · Co. Dublin
2, Olivemount Terrace, Dublin 14, D14P3K0
Granted 12 Oct 2023
Key facts
- Planning application D23B/0387 at 2, Olivemount Terrace, Dublin 14, D14P3K0: Renovate existing dwelling and construct a new extension to the rear…
- It was received by Dun Laoghaire Rathdown County Council on 18 Aug 2023.
- Status: Granted 12 Oct 2023.
- Work started on site on 29 Sep 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Dun Laoghaire Rathdown County Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 14 · Planning applications in Co. Dublin
Since you last looked
Worked out in this browser from the record's own dates. We do not send emails about it.
Council register
The council's register shows: Granted on 12 Oct 2023.
Search the Dun Laoghaire Rathdown planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Renovate existing dwelling and construct a new extension to the rear…
Renovate existing dwelling and construct a new extension to the rear of property
- Location
- Dublin 14, Co. Dublin Map
- Planning reference
- D23B/0387
Numbers and dates
- Homes
- ~1estimated from the application
- Project type
- One-off house
- Received
- 18 Aug 2023
- Granted
- 12 Oct 2023
- Site start
- 29 Sep 2026
Timeline
- Application received
- Granted
- Site start
Outlook
What happens next
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference D23B/0387.Search the register
How we know this
From the Dun Laoghaire Rathdown County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 29 Sep 2026Work started · Renovate existing dwelling and construct a new extension to the rear of property...
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.