Infrastructure · Co. Dublin
Leopardstown Road, Tipperstown, Dublin 18
Granted 30 Jun 2025 (final grant issued 7 Aug 2025)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 18 by email
Key facts
- Planning application D25A/0137/WEB at Leopardstown Road, Tipperstown, Dublin 18: Single storey ESB substation & s.
- It was received by Dun Laoghaire Rathdown County Council on 20 Feb 2025.
- Status: Granted 30 Jun 2025 (final grant issued 7 Aug 2025).
- Work was due to start on 29 Jul 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Dun Laoghaire Rathdown County Council planning register, as last seen on 6 Oct 2026. Search the council's register
More planning applications in Dublin 18 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 30 Jun 2025.
Search the Dun Laoghaire Rathdown planning register
Application details as we last saw them in the national register on 6 Oct 2026.
What and where
Single storey ESB substation & s
Permission is sought for the construction of a single storey ESB substation & s
This description may be shortened. The full text is in the council's planning file.
- Location
- Dublin 18, Co. Dublin Map
- Planning reference
- D25A/0137/WEB
Numbers and dates
- Project type
- Infrastructure
- Received
- 20 Feb 2025
- Decision to grant
- 30 Jun 2025
- Final grant
- 7 Aug 2025
- Site start notified
- 29 Jul 2026
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference D25A/0137/WEB.Search the register
How we know this
From the Dun Laoghaire Rathdown County Council planning register, as last seen on 6 Oct 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 29 Jul 2026Notice filed · Construction of 1no. single storey standalone building comprising an ESB Networks...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.