- Planning application D25A/0695/WEB at 61, Mount Anville Wood, Goatstown, Dublin 14, D14TY86: Single-storey extension to the front.
- It was received by Dun Laoghaire Rathdown County Council on 8 Sep 2025.
- Status: Granted 29 Oct 2025.
- Work started on site on 28 Aug 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Dun Laoghaire Rathdown County Council planning register, as last seen on 13 Oct 2026. Search the council's register
More planning applications in Dublin 14 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 29 Oct 2025.
Application details as we last saw them in the national register on 13 Oct 2026.
What and where
Single-storey extension to the front
Construction of a single-storey extension to the front at ground level and a two
- Location
- Dublin 14, Co. Dublin Map
- Planning reference
- D25A/0695/WEB
Numbers and dates
- Project type
- Planning record
- Received
- 8 Sep 2025
- Granted
- 29 Oct 2025
- Site start
- 28 Aug 2026
Timeline
- Application received
- Granted
- Site start
Outlook
What happens next
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference D25A/0695/WEB.Search the register
How we know this
From the Dun Laoghaire Rathdown County Council planning register, as last seen on 13 Oct 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 28 Aug 2026Work started · Construction of a single-storey extension to the front at ground level and a two-storey...View the site start