Planning record · Co. Dublin

Palmer Avenue, Adjacent to Kenure Crescent, Rush, Co Dublin

Granted 22 Oct 2015 (final grant issued 30 Nov 2015)

We no longer update this application, so we can't email you about it. Get new planning applications in Rush by email

Key facts

  • Planning application F15A/0231 at Palmer Avenue, Adjacent To Kenure Crescent, Rush, Co Dublin: New two-storey four-bedroom.
  • It was received by Fingal County Council on 25 Sep 2015.
  • Status: Granted 22 Oct 2015 (final grant issued 30 Nov 2015).

Source: the Fingal County Council planning register, as last seen on 2 Jun 2026. Search the council's register

More planning applications in Rush · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 22 Oct 2015.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

New two-storey four-bedroom

Permission for construction of a new two-storey four-bedroom

Location
Rush, Co. Dublin Map
Planning reference
F15A/0231

Numbers and dates

Project type
Planning record
Received
25 Sep 2015
Decision to grant
22 Oct 2015
Final grant
30 Nov 2015
Site start notified
8 Aug 2016

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference F15A/0231.Search the register

How we know this

From the Fingal County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 8 Aug 2016Notice filed · Construction of a new two-storey detached house on a green field siteView the site start
  2. Completion certificate recordedRecorded in Aug 2016 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Rush

Get alerts for RushFree. We email you when new applications appear.

Free email alerts

Get new Rush projects by email

New applications, decisions and site starts in Rush, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options