Commercial new build · Co. Dublin
SIte D4-D7, Horizon Logistics Park, off the R108 at Harristown, St Mar, Co. Dublin
Granted 24 Jul 2017 (final grant issued 28 Aug 2017)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Dublin by email
Key facts
- Planning application F17A/0308 at SIte D4-D7, Horizon Logistics Park, Off The R108 At Harristown, St Mar, Co. Dublin: 4 no. warehouse/logisctics buildin.
- It was received by Fingal County Council on 30 May 2017.
- Status: Granted 24 Jul 2017 (final grant issued 28 Aug 2017).
Source: the Fingal County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 24 Jul 2017.
Search the Fingal planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
4 no. warehouse/logisctics buildin
Permission for the construction of 4 no. warehouse/logisctics buildin
- Location
- St Mar, Co. Dublin Map
- Council
- Fingal County Council
- Planning reference
- F17A/0308
Numbers and dates
- Project type
- Commercial new build
- Received
- 30 May 2017
- Decision to grant
- 24 Jul 2017
- Final grant
- 28 Aug 2017
- Site start notified
- 2 Oct 2017
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference F17A/0308.Search the register
How we know this
From the Fingal County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 2 Oct 2017Notice filed · phase 1 · Unit D4 includes warehouse / logistics floorspace of approximately 3500 sq.m and...View the site start
- 10 Oct 2017Notice filed · phase 2 · Unit D5 includes warehouse / logistics floor space of approximately 2,629 sq.m and...View the site start
- 30 Aug 2018Notice filed · phase 3 · Unit D6 includes warehouse / logistics floorspace of approximately 1756m2 and ancillary...View the site start
- 3 Sep 2018Notice filed · phase 4 · Unit D7 includes warehouse / logistics floorspace space of approximately 2629m2 and...View the site start
- 20 Sep 2018Notice filed · phase 5 · Construction of an ESB Sub-StationView the site start
- Completion certificate recordedRecorded in Oct 2017 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Oct 2017 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.