- Planning application F18A/0718 at Charlestown Centre, Charlestown Place & St Margaret's Road, Charleston, Co. Dublin: Modifications to the Phase 2B application.
- It was received by Fingal County Council on 17 Dec 2018.
- Status: Granted 15 Feb 2019 (final grant issued 26 Mar 2019).
Source: the Fingal County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 15 Feb 2019.
Search the Fingal planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Modifications to the Phase 2B application
Modifications to the Phase 2B application (Reg. Ref. F18A/0025) to pro
- Location
- Charleston, Co. Dublin Map
- Council
- Fingal County Council
- Planning reference
- F18A/0718
Numbers and dates
- Project type
- Planning record
- Received
- 17 Dec 2018
- Decision to grant
- 15 Feb 2019
- Final grant
- 26 Mar 2019
- Site start notified
- 7 Sep 2019
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Site history
This site's history
-
Earlier permission F18A/0025 for this site: granted 16 Mar 2018.
Modifications to the recently permitted Phase 2B development (Reg. Ref Named in this application's description
Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference F18A/0718.Search the register
How we know this
From the Fingal County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 7 Sep 2019Notice filed · phase 1 · Apartments 559-681 Block U, Apartments 501-558 Block W & Apartments 772-819 Block T...View the site start
- 7 Sep 2019Notice filed · phase 2 · Apartments 682-727 Block R & Apartments 728-771 Block S, Charlestown, Finglas, Dublin...View the site start
- Completion certificate recordedRecorded in Sep 2019 · 90 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Sep 2019 · 123 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Sep 2019 · 58 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.