Public / civic · Co. Dublin
St Josephs Secondary School, Convent Lane, Rush, Co Dublin
Granted 15 Apr 2019 (final grant issued 22 May 2019)
We no longer update this application, so we can't email you about it. Get new planning applications in Rush by email
Key facts
- Planning application F19A/0094 at St Josephs Secondary School, Convent Lane, Rush, Co Dublin: Demolition of an existing single storey studio building.
- It was received by Fingal County Council on 27 Feb 2019.
- Status: Granted 15 Apr 2019 (final grant issued 22 May 2019).
Source: the Fingal County Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Rush · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 15 Apr 2019.
Search the Fingal planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Demolition of an existing single storey studio building
For demolition of an existing single storey studio building (floor are
- Location
- Rush, Co. Dublin Map
- Council
- Fingal County Council
- Planning reference
- F19A/0094
Numbers and dates
- Project type
- Public / civic
- Received
- 27 Feb 2019
- Decision to grant
- 15 Apr 2019
- Final grant
- 22 May 2019
- Site start notified
- 1 Mar 2021
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference F19A/0094.Search the register
How we know this
From the Fingal County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 1 Mar 2021Notice filed · construction/installation of two new single storey prefabricated classroom buildings and...View the site start
- Completion certificate recordedRecorded in Mar 2021 · 2 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.