Infrastructure · Co. Dublin
Hertz Compound, Airport Business Park, Cloghran, Co. Dublin, K67 C8V0.
Granted 16 Nov 2022 (final grant issued 19 Dec 2022)
We no longer update this application, so we can't email you about it. Get new planning applications in Cloghran by email
Key facts
- Planning application F22A/0510 at Hertz Compound, Airport Business Park, Cloghran, Co. Dublin, K67 C8V0.: Installation of an ESB substation and switchroom.
- It was received by Fingal County Council on 26 Sep 2022.
- Status: Granted 16 Nov 2022 (final grant issued 19 Dec 2022).
- Work was due to start on 30 Jan 2023, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Fingal County Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Cloghran · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 16 Nov 2022.
Search the Fingal planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Installation of an ESB substation and switchroom
The installation of an ESB substation and switchroom on site.
- Location
- Cloghran, Co. Dublin Map
- Council
- Fingal County Council
- Planning reference
- F22A/0510
Numbers and dates
- Project type
- Infrastructure
- Received
- 26 Sep 2022
- Decision to grant
- 16 Nov 2022
- Final grant
- 19 Dec 2022
- Site start notified
- 30 Jan 2023
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference F22A/0510.Search the register
How we know this
From the Fingal County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 30 Jan 2023Notice filed · the proposed erection of an ESB Substation and Switch room on siteView the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area