Zone 7, Hansfield SDZ, Hansfield, Dublin 15
Granted 17 Jun 2019
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 15 by email
Key facts
- Planning application FW18A/0161 at Zone 7, Hansfield SDZ, Hansfield, Dublin 15: Hansfield Investments Ltd intend to apply for planning permission.
- It was received by Fingal County Council on 29 Apr 2019.
- Status: Granted 17 Jun 2019.
Source: the Fingal County Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 15 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 17 Jun 2019.
Search the Fingal planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Hansfield Investments Ltd intend to apply for planning permission
Hansfield Investments Ltd intend to apply for planning permission for
- Location
- Dublin 15, Co. Dublin Map
- Council
- Fingal County Council
- Planning reference
- FW18A/0161
Numbers and dates
- Project type
- Planning record
- Received
- 29 Apr 2019
- Granted
- 17 Jun 2019
- Site start notified
- 16 Jun 2022
Timeline
- Application received
- Granted
- Site start notified
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference FW18A/0161.Search the register
How we know this
From the Fingal County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 16 Jun 2022Notice filed · The development will consist of the construction of 247 no. apartments in a building...View the site start
- Partial completion certificate recordedRecorded in Jun 2022 · 93 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Partial completion certificate recordedRecorded in Jun 2022 · 76 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Partial completion certificate recordedRecorded in Jun 2022 · 77 units on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.