One-off house · Co. Dublin
Former Clyde House, IDA Blanchardstown Business and Technology Park, S, Co. Dublin
Granted 13 Oct 2020 (final grant issued 18 Nov 2020)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Dublin by email
Key facts
- Planning application FW20A/0087 at Former Clyde House, IDA Blanchardstown Business and Technology Park, S, Co. Dublin: 3 no. data hall buildings with ancillary offices.
- It was received by Fingal County Council on 16 Sep 2020.
- Status: Granted 13 Oct 2020 (final grant issued 18 Nov 2020).
Source: the Fingal County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 13 Oct 2020.
Search the Fingal planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
3 no. data hall buildings with ancillary offices
Construction of 3 no. data hall buildings with ancillary offices, staf
- Location
- Co. Dublin Map
- Council
- Fingal County Council
- Planning reference
- FW20A/0087
Numbers and dates
- Homes
- ~1estimated from the application
- Project type
- One-off house
- Received
- 16 Sep 2020
- Decision to grant
- 13 Oct 2020
- Final grant
- 18 Nov 2020
- Site start notified
- 9 Feb 2021
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference FW20A/0087.Search the register
How we know this
From the Fingal County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 9 Feb 2021Notice filed · Construction of a new data centre facility on a site at Blanchardstown Business and...View the site start
- Partial completion certificate recordedRecorded in Feb 2021 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Partial completion certificate recordedRecorded in Feb 2021 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.