Planning record · Co. Dublin
Lands in the Townlands of Kellystown and Porterstown, Dublin 15
Granted 20 Nov 2025 (final grant issued 3 Feb 2026)
Key facts
- Planning application FW25A/0419E at Lands In The Townlands of Kellystown and Porterstown, Dublin 15: Permission.
- It was received by Fingal County Council on 26 Sep 2025.
- Status: Granted 20 Nov 2025 (final grant issued 3 Feb 2026).
- Work started on site on 22 Jul 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Fingal County Council planning register, checked 2 Jun 2026. Open the council's file
More planning applications in Dublin 15 · Planning applications in Co. Dublin
What and where
Permission
Permission at site (c. 2.17 ha) in the townlands of Porterstown and Ke
- Location
- Dublin 15, Co. Dublin Map
- Council
- Fingal County Council
- Planning reference
- FW25A/0419E
Numbers and dates
- Project type
- Planning record
- Received
- 26 Sep 2025
- Decision to grant
- 20 Nov 2025
- Final grant
- 3 Feb 2026
- Site start
- 22 Jul 2026
Timeline
- Application received
- Decision to grant
- Final grant issued
- Appeal decidedContribution Appeal Decided
- Site start
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file FW25A/0419E on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
- AppealContribution Appeal Decided · 500486 / 12 Jun 2026View the appeal record
How we know this
From the Fingal County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.
Site starts
Commencement notices for this permission
- Site startWork started · phase 1 · Construction of 35no. units and all associated site works as described in planning...The recorded date is not shown because it is out of sequence with the other steps.View the site start
- 22 Jul 2026Work started · phase 2 · Construction of a three-storey residential block (Block J) forming part of the...View the site start
- 31 Jul 2026Work started · phase 3 · Construction of a three-storey residential block (Block H) forming part of the...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area