Planning record · Co. Dublin
Lands to the south of Back Road and to the east of Kinsealy Lane, Kins, Co. Dublin
Granted 24 Jan 2025
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Dublin by email
Key facts
- Planning application LRD0043/S3E at Lands To The South of Back Road and To The East of Kinsealy Lane, Kins, Co. Dublin: Planning application.
- It was received by Fingal County Council on 21 Nov 2024.
- Status: Granted 24 Jan 2025.
- Work started on site on 29 May 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Fingal County Council planning register, as last seen on 5 Oct 2026. Search the council's register
Council register
The council's register shows: Granted on 24 Jan 2025.
Search the Fingal planning register
Application details as we last saw them in the national register on 5 Oct 2026.
What and where
Planning application
We, Birchwell Developments Ltd., intend to apply for permission for a
- Location
- Kins, Co. Dublin Map
- Council
- Fingal County Council
- Planning reference
- LRD0043/S3E
Numbers and dates
- Project type
- Planning record
- Received
- 21 Nov 2024
- Granted
- 24 Jan 2025
- Site start
- 29 May 2026
Timeline
- Application received
- Granted
- Appeal lodged
- Appeal decidedAppeal withdrawn S.140(1)(a)
- Site start
Outlook
What happens next
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference LRD0043/S3E.Search the register
- AppealAppeal withdrawn S.140(1)(a) · 321932 / 23 May 2025View the appeal record
How we know this
From the Fingal County Council planning register, as last seen on 5 Oct 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 29 May 2026Work started · phase 1 · Construction of units 1-2 Old Orchard Drive part of the overall residential development...View the site start
- 2 Jun 2026Work started · phase 2 · Construction of 6 new dwelling houses and associated site works, 3 to 8 incl. Old...View the site start
- 16 Sep 2026Work started · phase 3 · Construction of Shell and Core Childcare Facility as permitted under planning permission...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.