Final grant dated 10 August 2026; submitted October-November 2025 technical reports predate June 2026 further information.
The final amendment grant records 83 homes, five above the earlier permission
Final amendment grant recorded · Current amendment and earlier permission; no additive project total
What the evidence says
The final grant dated 10 August 2026 records a decision of 29 June 2026 on LRD26A/0001W. It amends LRD24A/0001 / ABP-319568-24, with a revised total of 83 homes compared with 78 previously granted and 100 originally applied for. The description identifies 79 apartments and four duplex homes, reduced basement footprint, altered roof profiles and a relocated substation. Condition 1 incorporates further information received on 2 June 2026; condition 2 retains the earlier permission except where amended. The 83 are a revised total, not an additional 83 homes.
Why it may matter — interpretation
Design teams and quantity surveyors can separate the five-home increase and changed interfaces from the retained development.
What is not established
Construction, the full June further-information drawing set and subsequent compliance submissions have not been verified.
Inspect the evidence
Firhouse LRD amendment: final grant · p.1
increase of 5 no. units · Issued 2026-08-10 · Final grant 10 August; underlying council decision 29 June; June 2 further information incorporated · Checked 2026-09-06
increase of 5 no. units
Firhouse LRD amendment: final grant · p.2
as amended by · Issued 2026-08-10 · Final grant 10 August; underlying council decision 29 June; June 2 further information incorporated · Checked 2026-09-06
as amended by
The submitted energy strategy proposes air-source heat pumps and MVHR
Submitted report predates the June 2026 revisions · October 2025 submitted apartment-services strategy
What the evidence says
The energy statement, revision R2 dated 22 October 2025 and received on 12 February 2026, proposes air-source heat pumps for apartment heating and hot water, with mechanical ventilation and heat recovery. It describes heat-recovery capability up to 85%, which is a proposed performance basis, not a measured result. This report predates the June 2026 further information incorporated into the final grant.
Why it may matter — interpretation
M&E designers and heat-pump or ventilation suppliers can identify the proposed system families and the later design confirmation needed.
What is not established
Final equipment, capacity, acoustic design, selected manufacturer and commissioned performance are unverified.
Inspect the evidence
Firhouse energy and sustainability design statement · p.4
air-source heat pumps · Issued 2025-10-22 · R2 updated layouts; received 12 February 2026; PV feasibility conflict retained · Checked 2026-09-06
air-source heat pumps
Firhouse energy and sustainability design statement · p.15
up to 85% · Issued 2025-10-22 · R2 updated layouts; received 12 February 2026; PV feasibility conflict retained · Checked 2026-09-06
up to 85%
The PV narrative and feasibility column disagree
Unresolved source disagreement · Internal disagreement within the October 2025 energy statement
What the evidence says
The energy summary proposes roof-mounted PV serving landlord and common areas. Page 18 also says mono-crystalline PVs are proposed, but the same table marks the photovoltaic option "No" in its feasibility column. This disagreement is retained rather than treating PV as finally selected. No panel count, array capacity or later approved selection has been established.
Why it may matter — interpretation
PV designers and electrical engineers can identify the specification question that needs clarification before sizing an array.
What is not established
Whether the feasibility marker is an error, and what the June revision or later compliance design selects, remain unknown.
Inspect the evidence
Firhouse energy and sustainability design statement · p.18
Mono-crystalline PVs are proposed · Issued 2025-10-22 · R2 updated layouts; received 12 February 2026; PV feasibility conflict retained · Checked 2026-09-06
Mono-crystalline PVs are proposed
BER and airtightness values remain design targets
Submitted report predates the June 2026 revisions · October 2025 proposed performance basis
What the evidence says
The submitted statement targets BER A2/A3 across dwellings and an air-permeability rate of 3.0 m3/hr/m2. These are the report’s design targets for a fabric-first approach; they are not completed-building certificates or test results.
Why it may matter — interpretation
Envelope designers and energy assessors can compare the targets with later calculations and airtightness specifications.
What is not established
Final BER calculations, tested permeability and as-built energy performance are unverified.
Inspect the evidence
Firhouse energy and sustainability design statement · p.4
Target BER A2/A3 · Issued 2025-10-22 · R2 updated layouts; received 12 February 2026; PV feasibility conflict retained · Checked 2026-09-06
Target BER A2/A3
Firhouse energy and sustainability design statement · p.15
air permeability rate · Issued 2025-10-22 · R2 updated layouts; received 12 February 2026; PV feasibility conflict retained · Checked 2026-09-06
air permeability rate
The drainage proposal names an 80 m3 tank and a 2 l/s control
Submitted report predates the June 2026 revisions · October 2025 submitted surface-water design, before June further information
What the evidence says
The civil report P02 dated 24 October 2025 proposes an 80 m3 attenuation tank beneath the southern parking area, using StormTech or similar approved. It describes modular plastic chambers surrounded by clean washed aggregate and discharge controlled by a Hydrobrake at 2 l/s. These are submitted design values, not installed capacity or evidence of a product order.
Why it may matter — interpretation
Drainage designers and attenuation suppliers can compare the chamber system, storage and controlled outflow with the later agreed design.
What is not established
The final chamber selection, hydraulic revision, discharge agreement and installed tank are unverified.
Inspect the evidence
Firhouse civil engineering infrastructure report · p.9
StormTech attenuation tank · Issued 2025-10-24 · P02 issued for planning; received 12 February 2026 · Checked 2026-09-06
StormTech attenuation tank
Firhouse civil engineering infrastructure report · p.14
modular plastic chambers · Issued 2025-10-24 · P02 issued for planning; received 12 February 2026 · Checked 2026-09-06
modular plastic chambers
Roof storage and the ground-level tank are distinct parts of the design
Submitted report predates the June 2026 revisions · Separate roof and ground-level components of the October 2025 proposal
What the evidence says
The report proposes 0.15 m blue-roof build-ups with green and brown finishes. It estimates 144.33 m3 of roof-level storage across approximately 1,698 m2 of roof, draining through restricted outlets and podium pipework to the surface-water system. The separate 80 m3 tank receives residual runoff. The stated model basis includes a 1-in-100-year event, 20% climate-change allowance and 10% urban creep. These are historical design quantities, not verified constructed volumes.
Why it may matter — interpretation
Roofing and drainage designers can check outlet control, waterproofing and structural interfaces without confusing roof storage with tank capacity.
What is not established
Final roof build-up, structural loading, revised model and installed volumes remain unverified.
Inspect the evidence
Firhouse civil engineering infrastructure report · p.16
estimated 144.33m · Issued 2025-10-24 · P02 issued for planning; received 12 February 2026 · Checked 2026-09-06
estimated 144.33m
Firhouse civil engineering infrastructure report · p.9
0.15m deep blue roof · Issued 2025-10-24 · P02 issued for planning; received 12 February 2026 · Checked 2026-09-06
0.15m deep blue roof
The historical lighting report illustrates four named fitting families
Submitted report predates the June 2026 revisions · Historical November 2025 fitting illustrations, subject to the later lighting condition
What the evidence says
The lighting report revision 02 dated 3 November 2025 illustrates Thorn R2L2 road lighting at 15 W and 3000 K, Thorn EyeKon bulkheads at 16 W and 4000 K, Thorn Cesar Stroll bollards at 35.1 W and 2700 K, and a Simes Miniblinker recessed step light. These are submitted product illustrations, not an approved equipment schedule. The later council condition requires a fuller lighting model and written agreement; no installation count or final product selection is established.
Why it may matter — interpretation
Lighting designers and suppliers can identify the illustrated product families while checking the revised model before specification.
What is not established
Final fittings, quantities, colour-temperature strategy, procurement and installation are unverified.
Inspect the evidence
Firhouse public lighting report · p.6
Thorn R2L2 · Issued 2025-11-03 · Revision 02; earlier revision 01 dated 22 October; received 12 February 2026 · Checked 2026-09-06
Thorn R2L2
Firhouse public lighting report · p.7
Thorn EyeKon · Issued 2025-11-03 · Revision 02; earlier revision 01 dated 22 October; received 12 February 2026 · Checked 2026-09-06
Thorn EyeKon
Firhouse public lighting report · p.8
Thorn Cesar Stroll Bollard · Issued 2025-11-03 · Revision 02; earlier revision 01 dated 22 October; received 12 February 2026 · Checked 2026-09-06
Thorn Cesar Stroll Bollard
Firhouse public lighting report · p.9
Simes Miniblinker · Issued 2025-11-03 · Revision 02; earlier revision 01 dated 22 October; received 12 February 2026 · Checked 2026-09-06
Simes Miniblinker
The council requires the complete carriageway and existing lighting to be modelled
Recorded council condition · Final grant condition controlling the earlier submitted lighting design
What the evidence says
Condition 7 in the final grant says the proposed lighting design covers only footpaths and does not include the entire carriageway, which is not acceptable. Before commencement or lighting installation, a complete design, spill calculations and modelling of existing lighting and the whole carriageway must obtain written agreement. The historical report is therefore not treated as the final approved lighting scheme.
Why it may matter — interpretation
Lighting engineers can target the missing calculation areas and existing-asset interfaces in the required revised submission.
What is not established
The later agreed calculation file, revised layout and completed lighting have not been inspected.
Inspect the evidence
Firhouse LRD amendment: final grant · p.3
only the footpaths · Issued 2026-08-10 · Final grant 10 August; underlying council decision 29 June; June 2 further information incorporated · Checked 2026-09-06
only the footpaths
Selected pages of 4 government-published PDFs were visually inspected. Four supporting PDFs were retrieved from 180 listed documents. Selected pages were visually inspected; the complete June 2026 further-information set and later compliance records were not reviewed. Proposals do not establish procurement or installed work.