Infrastructure · Co. Dublin

Former Shinko Building, Greenhills Road, Tallaght, Dublin 24

Granted 12 Dec 2014 (final grant issued 19 Jan 2015)

We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 24 by email

Key facts

  • Planning application SD14A/0232 at Former Shinko Building, Greenhills Road, Tallaght, Dublin 24: New two storey c.11.
  • It was received by South Dublin County Council on 4 Nov 2014.
  • Status: Granted 12 Dec 2014 (final grant issued 19 Jan 2015).

Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Dublin 24 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 12 Dec 2014.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

New two storey c.11

Construction of a new two storey c.11,700sq.m building for use as electrical rooms for electronic operations, mechanical plant rooms and support areas including a loading bay, offices and welfare facilities; mechanical plant at roof level is screened from view on all sides; a new 50sq.m electrical substation; a new plant array along the east site boundary including an electrical substation transformer compound; a 90sq.m electrical substation control room; a diesel fuel tank farm and loading bay; a 10sq.m fuel pump house; a sprinkler water tank; a 70sq.m water pump house; a humidifier water tank farm; the repositioning and widening of vehicular entrances; 2 site entrances at changed locations in place of 3 existing; 23 car parking spaces, landscaping and ancillary works; the combined gross floor area of the proposed buildings totals c. 11,920sq.m; demolition of existing buildings is being carried out under grant of permission Reg. Ref. SD13A/0266.

Location
Dublin 24, Co. Dublin Map
Planning reference
SD14A/0232

Numbers and dates

Floor area
11,920 m²
Project type
Infrastructure
Received
4 Nov 2014
Decision to grant
12 Dec 2014
Final grant
19 Jan 2015
Site start notified
2 Feb 2015

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Documents and evidence

Check the record

  • Council planning fileThe application file SD14A/0232 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file

How we know this

From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 2 Feb 2015Notice filed · Construction of a new two-storey c.11,700 sq.m. building for use as electrical rooms for...View the site start
  2. Completion certificate recordedRecorded in Feb 2015The month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Last checked 20 Nov 2026.
  3. Full completion certificate recordedRecorded in Feb 2015 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers the work listed on the certificate; later phases can have their own. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 24

Get alerts for Dublin 24Free. We email you when new applications appear.

Free email alerts

Get new Dublin 24 projects by email

New applications, decisions and site starts in Dublin 24, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options