Infrastructure · Co. Dublin

former Jacobs/Allied Biscuits Site, Belgard Road, Tallaght, Dublin 24

Granted 2 Jun 2016 (final grant issued 7 Jul 2016)

We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 24 by email

Key facts

  • Planning application SD16A/0093 at Former Jacobs/Allied Biscuits Site, Belgard Road, Tallaght, Dublin 24: Redevelopment of the former single storey.
  • It was received by South Dublin County Council on 16 May 2016.
  • Status: Granted 2 Jun 2016 (final grant issued 7 Jul 2016).

Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Dublin 24 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 2 Jun 2016.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Redevelopment of the former single storey

(1) The redevelopment of the former single storey c. 20,892sq.m Jacob's factory building for use as electrical rooms for electronic operations, mechanical plant rooms and support areas including loading bays, stores, offices and welfare facilities. The development will also contain new external plant areas including; (2) back up generators; (3) two electrical substations; (4) an electrical transformer compound with associated control rooms; (5) a sprinkler water tank and pump house; (6) a humidifier water tank compound and pump house; (7) a fuel tank compound and pump house; (8) a security entrance kiosk; (9) two new vehicular and pedestrian entrances including a main entrance at Airton Road and an emergency entrance at Mayberry Road; (10) 120 car parking spaces; (11) the refurbishment of boundary railings, fencing, landscaping and (12) sundry ancillary works. Mechanical plant at roof level of the main building is screened from view on all sides. The combined gross floor area of all proposed buildings is 22,147sq.m. A seperate application for planning permission for the demolition of existing buildings has been lodged with South Dublin County Council - Reg. Ref. SD16A/0086.

Location
Dublin 24, Co. Dublin Map
Planning reference
SD16A/0093

Numbers and dates

Floor area
22,147 m²
Project type
Infrastructure
Received
16 May 2016
Decision to grant
2 Jun 2016
Final grant
7 Jul 2016
Site start notified
23 Aug 2016

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work packages named so far

  • Roads and site development worksNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file SD16A/0093 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file

How we know this

From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 23 Aug 2016Notice filed · (1) The redevelopment of the former single-storey c. 20,892 sq.m. Jacob’s factory...View the site start
  2. Partial completion certificate recordedRecorded in Aug 2016 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
  3. Partial completion certificate recordedRecorded in Aug 2016 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
  4. Partial completion certificate recordedRecorded in Aug 2016 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 24

Get alerts for Dublin 24Free. We email you when new applications appear.

Free email alerts

Get new Dublin 24 projects by email

New applications, decisions and site starts in Dublin 24, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options