Commercial fit-out · Co. Dublin

Units 6 & 7 Tower Shopping Centre, Tower Road, Clondalkin, Dublin 22

Granted 23 May 2016 (final grant issued 4 Jul 2016)

We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 22 by email

Key facts

  • Planning application SD16A/0098 at Units 6 & 7 Tower Shopping Centre, Tower Road, Clondalkin, Dublin 22: Change of use of Unit 6 from cafe/takeaway to pizza bakery.
  • It was received by South Dublin County Council on 30 Mar 2016.
  • Status: Granted 23 May 2016 (final grant issued 4 Jul 2016).

Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Dublin 22 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 23 May 2016.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Change of use of Unit 6 from cafe/takeaway to pizza bakery

(a) Change of use of Unit 6 from cafe/takeaway to pizza bakery; (b) interconnection with existing pizza takeaway shop in Unit 7 by forming openings in the dividing walls between the units; (c) new shopfronts and co-ordinated signage for the combined premises.

Location
Dublin 22, Co. Dublin Map
Planning reference
SD16A/0098

Numbers and dates

Floor area
63 m²
Estimated construction value
€50k to €130kOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Commercial fit-out
Received
30 Mar 2016
Decision to grant
23 May 2016
Final grant
4 Jul 2016
Site start notified
8 Sep 2016

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Documents and evidence

Check the record

  • Council planning fileThe application file SD16A/0098 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file

How we know this

From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 8 Sep 2016Notice filed · (a) change-of-use of Unit 6 from cafe/takeaway to pizza bakery (b) interconnection with...View the site start
  2. Completion certificate recordedRecorded in Sep 2016 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 22

Get alerts for Dublin 22Free. We email you when new applications appear.

Free email alerts

Get new Dublin 22 projects by email

New applications, decisions and site starts in Dublin 22, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options