Planning record · Co. Dublin
Grange Castle Business Park, Nangor Road, Clondalkin, Dublin 22.
Granted 31 Aug 2016 (final grant issued 10 Oct 2016)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 22 by email
Key facts
- Planning application SD16A/0236 at Grange Castle Business Park, Nangor Road, Clondalkin, Dublin 22.: New 5 storey bio-pharmaceutical manufacturing building to be built…
- It was received by South Dublin County Council on 8 Jul 2016.
- Status: Granted 31 Aug 2016 (final grant issued 10 Oct 2016).
- Work was due to start on 25 Oct 2016, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Dublin 22 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 31 Aug 2016.
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
New 5 storey bio-pharmaceutical manufacturing building to be built…
A new 5 storey bio-pharmaceutical manufacturing building to be built in two phases. Phase 1 sized 20,320sq.ms and 28.2 meters high including a single storey link sized 1,203sq.m, and Phase 2 sized 14,320sq.m and 28.2 meters high, including a single storey link sized 750sq.m, located to the south of their existing Drug Substance Building. A single storey warehouse extension located to the south of the existing warehouse including new docking facilities sized 1,142sq.m and 11.2 meter high. A three storey extension located to the east of the existing laboratory building sized 1,328sq.m and 17.6 meters high. A new south elevation with new windows on the fourth floor of the existing drug substance building. New site works including 565 new car parking spaces of which 282 are relocated car parking spaces - 282 spaces lost due to the development footprint - located to the north of the site, together with a new bicycle parking facility, a new permanent heavy goods entrance at the current construction entrance to the south boundary of the campus and new fencing, 2.1 meters high, to the east, west and south side boundaries. Permanent car parking of 350 spaces for sustaining construction and contract personnel utilising a portion of the existing temporary contractor car park. Upon completion of the construction and commissioning activities, the remainder of the contractor car park will be decommissioned. A new single storey security building sized 56sq.m and revisions and alterations to the existing road, services and landscaping and new items of plant and equipment located in the existing and proposed yards, and associated pipe bridges. All associated site works. A 10 year planning permission is sought for this proposed development. The application consists of a variation to a previously permitted development on an activity for which a licence under Part IV of the Environmental Protection Agency Act 1992 (as amended for the Protection of the Environment Act 2003) is required and full details of the proposed development and its anticipated environmental impacts will be notified to the Environmental Protection Agency. An Environmental Impact Statement accompanies this application, and it will be avialable for inspection or purchase at the office of the Planning Authority.
- Location
- Dublin 22, Co. Dublin Map
- Council
- South Dublin County Council
- Planning reference
- SD16A/0236
Numbers and dates
- Floor area
- 37,166 m²
- Project type
- Planning record
- Received
- 8 Jul 2016
- Decision to grant
- 31 Aug 2016
- Final grant
- 10 Oct 2016
- Site start notified
- 25 Oct 2016
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file SD16A/0236 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 25 Oct 2016Notice filed · phase 1 · Non-building works associated with the development subject to Planning Permission Ref...View the site start
- 26 Oct 2016Notice filed · phase 2 · New 5 storey bio- pharmaceutical manufacturing building - DS2 - Phase 1. 20,320 sq...View the site start
- 8 May 2023Notice filed · phase 3 · Enabling works including modifications and extensions to existing service plant for New...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.