Public / civic · Co. Dublin
Holy Spirit Junior Primary School, Greenhills, Walkinstown, Dublin 12
Granted 8 Aug 2017 (final grant issued 18 Sep 2017)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 12 by email
Key facts
- Planning application SD17A/0184 at Holy Spirit Junior Primary School, Greenhills, Walkinstown, Dublin 12: Installation of four single storey temporary prefabricated classroom…
- It was received by South Dublin County Council on 14 Jun 2017.
- Status: Granted 8 Aug 2017 (final grant issued 18 Sep 2017).
- Work was due to start on 16 Feb 2018, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Dublin 12 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 8 Aug 2017.
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Installation of four single storey temporary prefabricated classroom…
Installation of four single storey temporary prefabricated classroom buildings including all associated site works.
- Location
- Dublin 12, Co. Dublin Map
- Council
- South Dublin County Council
- Planning reference
- SD17A/0184
Numbers and dates
- Floor area
- 384 m²
- Project type
- Public / civic
- Received
- 14 Jun 2017
- Decision to grant
- 8 Aug 2017
- Final grant
- 18 Sep 2017
- Site start notified
- 16 Feb 2018
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file SD17A/0184 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 16 Feb 2018Notice filed · Proposed temporary prefabricated classroom building (4 Classrooms) at Holy Spirit Junior...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area