Large residential · Co. Dublin

Green Lane, Rathcoole, Co. Dublin.

Granted on appeal 7 Nov 2018 (Decision to grant 9 Apr 2018 by the council)

We no longer update this application, so we can't email you about it. Get new planning applications in Rathcoole by email

Key facts

  • Planning application SD17A/0356 at Green Lane, Rathcoole, Co. Dublin.: 69 homes.
  • It was received by South Dublin County Council on 12 Mar 2018.
  • Status: Granted on appeal 7 Nov 2018 (Decision to grant 9 Apr 2018 by the council).

Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Rathcoole · Planning applications in Co. Dublin

Council register

The council's register shows: Decision to grant on 9 Apr 2018.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

69 homes

The construction of a residential development of 69 units comprising: 52 houses in a mix of terraced, semi-detached and detached (comprising 6 three bed units, 8 three bed units with study and 38 four bed units) of 2 storeys (including second floor accommodation in roof space with dormer windows and roof lights) and 17 apartments (4 one beds, 12 two beds and 1 3-bed) in 3 blocks of 3 storeys. The apartments include balconies at first and second floor level and dormer windows at second level. The proposed development includes associated public open space, landscaping including boundary treatment, underground services and utilities and road, footpath and cycle infrastructure on the site. 132 surface car parking spaces will be provided for the development, in a combination of in-curtilage and grouped parking. The apartments are provided with 21 sheltered bicycle parking spaces and refuse storage areas. The proposed development includes amendments to the existing roadway at St. Anne's Terrace and amendments and upgrades to Green Lane, including provision of new footpath on Green Lane along with new development entrance piers at the entrance to the proposed development. The total gross floor area of the proposed development will be circa 10,086sq.m at this circa 2.4 hectare site bounded to the west by Green Lane, to the north-west by St. Anne's Terrace and Blackthorn Hill residential estate, to the east by Rathcoole Boys Football Club and to the south by greenfield lands. The site is accessed from Green Lane to the west of the site. The site also includes part of the Rathcoole Boys Football Club lands and Forest Hills required for connection to the sewer network.

Location
Rathcoole, Co. Dublin Map
Planning reference
SD17A/0356

Numbers and dates

Homes
69
Floor area
10,086 m²
Estimated construction value
€17m to €32mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Large residential
Received
12 Mar 2018
Council decision
9 Apr 2018
Appeal lodged
2 May 2018
Granted on appeal
7 Nov 2018
Site start notified
6 Dec 2018

Timeline

  1. Application received
  2. Decision to grant by the council
  3. Appeal lodged
  4. Appeal decidedGrant permission with revised conditions
  5. Site start notified

Outlook

What happens next

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file SD17A/0356 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
  • AppealGrant permission with revised conditions · 301541 / 7 Nov 2018View the appeal record

How we know this

From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 6 Dec 2018Notice filed · phase 1 · The construction of 1-12 The Square, 1-4 The Drive, 28-33 The Square, 21-46 The AvenueView the site start
  2. 31 Jan 2019Notice filed · phase 2 · 5 The Drive, 25-27 The Square, 47&48 The AvenueView the site start
  3. 24 May 2019Notice filed · phase 3 · The construction of two apartment blocks, 13-24 The Square and 6-14 The Drive, Greenlane...View the site start
  4. Completion certificate recordedRecorded in Dec 2018 · 12 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
  5. Completion certificate recordedRecorded in Dec 2018 · 3 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
  6. Completion certificate recordedRecorded in Dec 2018 · 6 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Rathcoole

Get alerts for RathcooleFree. We email you when new applications appear.

Free email alerts

Get new Rathcoole projects by email

New applications, decisions and site starts in Rathcoole, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options