  • Planning application SD17A/0469 at Greenhills Business Park, Greenhills Road, Dublin 24: New 2 storey building for use as a data storage facility.
  • It was received by South Dublin County Council on 22 Dec 2017.
  • Status: Granted 26 Feb 2018 (final grant issued 4 Apr 2018).

Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Dublin 24 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 26 Feb 2018.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

New 2 storey building for use as a data storage facility

Construction of a new 2 storey building (c.8229sq.m) for use as a data storage facility. The new facility will be an annex to, and accessed through, the neighbouring data storage facility to the north via the existing site entrance serving same. The development will include electrical rooms for electronic operations, mechanical plant rooms and support areas including offices and welfare facilities, a loading bay and back-up generators in a fenced compound. Existing boundary structures including railings, fencing and gates will be replaced with a new 3, high perimeter railing. Ventilation plant at roof level will be screened from view on all sides (all at the former Barretts site).

Location
Dublin 24, Co. Dublin Map
Planning reference
SD17A/0469

Numbers and dates

Floor area
8,229 m²
Estimated construction value
€27m to €39mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Commercial new build
Received
22 Dec 2017
Decision to grant
26 Feb 2018
Final grant
4 Apr 2018
Site start notified
16 Jul 2018

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Documents and evidence

Check the record

  • Council planning fileThe application file SD17A/0469 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file

How we know this

From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 16 Jul 2018Notice filed · The proposed development will include the construction of a new two-storey building...View the site start
  2. Partial completion certificate recordedRecorded in Jul 2018 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
  3. Partial completion certificate recordedRecorded in Jul 2018 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 24

Get alerts for Dublin 24Free. We email you when new applications appear.

Free email alerts

Get new Dublin 24 projects by email

New applications, decisions and site starts in Dublin 24, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options