Key facts
- Planning application SD18A/0036 at Unit 527, Grants Hill, Greenogue Business Park, Greenogue, Rathcoole, Dublin: Warehouse unit 6.
- It was received by South Dublin County Council on 17 May 2018.
- Status: Granted 13 Jun 2018 (final grant issued 23 Jul 2018).
Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Rathcoole · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 13 Jun 2018.
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Warehouse unit 6
Warehouse unit 6,461sq.m, 17.40m high with 568sq.m integrated ancillary offices/staff facilities on 3 floors plus 763sq.m mezzanine storage area to warehouse totalling 7,792sq.m. The development will also include: (a) Site access from Grants Hill, (b) On-site security hut 14.50sq.m, 3m high, (c) Ancillary car parking, (d) HGV marshalling yard & HGV parking facility for 12 vehicles 816sq.m, (e) Site landscaping, (f) Flood management measures, (g) Drainage works including underground surface water attenuation facility, (h) all services & utilities including ESB sub-station 9sq.m, 3m high, (i) Plus all associated site development works.
- Location
- Rathcoole, Co. Dublin Map
- Council
- South Dublin County Council
- Planning reference
- SD18A/0036
Numbers and dates
- Floor area
- 7,816 m²
- Estimated construction value
- €9.5m to €12mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Commercial new build
- Received
- 17 May 2018
- Decision to grant
- 13 Jun 2018
- Final grant
- 23 Jul 2018
- Site start notified
- 6 Dec 2018
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file SD18A/0036 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 6 Dec 2018Notice filed · The development consists of the construction of a new 6,461m.sq. warehouse with...View the site start
- Completion certificate recordedRecorded in Dec 2018 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.