Infrastructure · Co. Dublin
Aerodrome Business Park, Site Q2, Jordanstown Road, Collegeland, Rathcoole, Co. Dublin
Granted 10 Oct 2019 (final grant issued 18 Nov 2019)
We no longer update this application, so we can't email you about it. Get new planning applications in Rathcoole by email
Key facts
- Planning application SD19A/0264 at Aerodrome Business Park, Site Q2, Jordanstown Road, Collegeland, Rathcoole, Co. Dublin: Warehouse with ancillary three storey office and staff facilities…
- It was received by South Dublin County Council on 16 Aug 2019.
- Status: Granted 10 Oct 2019 (final grant issued 18 Nov 2019).
Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Rathcoole · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 10 Oct 2019.
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Warehouse with ancillary three storey office and staff facilities…
Warehouse with ancillary three storey office and staff facilities and associated development. The warehouse will have a parapet height of 17 metres with a gross floor area of 14,649sq.m including a warehouse area (13,494sq.m), ancillary office areas (1099sq.m) and staff facilities (56sq.m); provision of a new vehicular access/egress onto the Jordanstown Road; internal roadways; pedestrian access; 152 ancillary car parking spaces; bicycle parking; HGV yard including 26 HGV parking stands and 18 loading docks; hard and soft landscaping including green walls; lighting; photo-voltaic panels; ESB substation and switch room; plant; boundary treatments and associated development works above and below ground.
- Location
- Rathcoole, Co. Dublin Map
- Council
- South Dublin County Council
- Planning reference
- SD19A/0264
Numbers and dates
- Floor area
- 14,649 m²
- Project type
- Infrastructure
- Received
- 16 Aug 2019
- Decision to grant
- 10 Oct 2019
- Final grant
- 18 Nov 2019
- Site start notified
- 12 Jul 2021
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file SD19A/0264 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 12 Jul 2021Notice filed · phase 1 · UNIT Q2, Aerodrome, Construction of new Warehouse with 3-storey ancillary officesView the site start
- 7 Oct 2021Notice filed · phase 2 · New ESB Sub- stationView the site start
- Completion certificate recordedRecorded in Jul 2021 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Oct 2021 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area