Infrastructure · Co. Dublin
Townlands within Grange Castle South Business Park, Baldonnel, Dublin 22
Granted 16 Mar 2021 (final grant issued 26 Apr 2021)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 22 by email
Key facts
- Planning application SD20A/0295 at Townlands Within Grange Castle South Business Park, Baldonnel, Dublin 22: Amendments and modifications to the permitted data centre development…
- It was received by South Dublin County Council on 17 Feb 2021.
- Status: Granted 16 Mar 2021 (final grant issued 26 Apr 2021).
Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Dublin 22 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 16 Mar 2021.
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Amendments and modifications to the permitted data centre development…
Amendments and modifications to the permitted data centre development granted under Reg. Ref. SD18A/0134 - ABP Ref. ABP-302813-18 and the temporary substation permission granted under SD19A/0300 to include: Demolition of the two storey dwelling of Weston House; single storey dwelling and outbuildings/ stables of Weston Lodge; and the single storey dwelling and converted garage of Kent Cottage. Retention of sprinkler tank and pump house to the south-west of Building A Data Centre to replace 4 sprinkler tanks; Retention of 40kW(p) PV panels on the roof of Building A Data Centre; Retention of revised size of northern attenuation pond and loss of permitted landscaping to its south; Retention of ramped access to rear of temporary substation permitted under SD19A/0300; Retention of revised flue arrangement for Building A Data Centre from 2 associated flues per generator to 1 associated flue per generator (16 in total) and grouped into 8 towers of two flues each (each 20m high); Retention of revised position of security fence to north, west and south of Building A Data Centre; and retention and modifications of landscape berm along Baldonnel Road and to east of Weston House. Development will consist of new works to include: Modifications of permitted vehicular entrance to the data centre to include a new single storey guard house (37sq.m) and two internal entrance gates; Modification to car parking so that the permitted entrance to the parking area from the east is closed off; Modifications of flue arrangement for Building B Data Centre from 2 associated flues per generator to 1 associated flue per generator (16 in total) and grouped into 8 towers of two flues each (each 20m high); Modifications to permitted landscape scheme to north and south of Building A Data Centre; Removal of roadside entrance to Erganagh House (demolished), Kent Cottage, and the former scaffolding yard; and removal of roadside entrance to Weston House and its replacement with a new agricultural gate and fence to be erected to facilitate access for maintenance and security purposes only all on a site of 9.7Ha located within lands in the Grange Castle South Business Park and the residential properties of Weston House, Kent Cottage and Weston Lodge as well as the former scaffolding yard on land within the townlands of Aungierstown and Ballybane; Ballybane; and Milltown and bounding Baldonnel Road to the west and south and Grange Castle South access road to the north, Baldonnel, Dublin 22.
- Location
- Dublin 22, Co. Dublin Map
- Council
- South Dublin County Council
- Planning reference
- SD20A/0295
Numbers and dates
- Floor area
- 37 m²
- Project type
- Infrastructure
- Received
- 17 Feb 2021
- Decision to grant
- 16 Mar 2021
- Final grant
- 26 Apr 2021
- Site start notified
- 18 May 2021
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Site history
This site's history
-
Earlier permission SD18A/0134 for this site: decision to grant 24 Sep 2018.
Demolition of the existing single storey house of 'Erganagh' and the construction of a two storey data centre and delivery bays with… Named in this application's description -
Earlier permission SD19A/0300 for this site: granted 18 Nov 2019.
Single storey ESB substation (27sq.m) that will be accessed from the north off the Grange Castle South Access Road via the Baldonnel Road… Named in this application's description
Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file SD20A/0295 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 18 May 2021Notice filed · CyrusOne Grange Castle Guard House, Grange Castle Business Park, Clondalkin, Dublin 22...View the site start
- Completion certificate recordedRecorded in May 2021 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.