Public / civic · Co. Dublin
Oldcourt Road/Ballycullen Green, Firhouse, Dublin 24
Granted on appeal 14 Feb 2022 (Decision to grant 20 Jul 2021 by the council)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 24 by email
Key facts
- Planning application SD21A/0137 at Oldcourt Road/Ballycullen Green, Firhouse, Dublin 24: Temporary two storey post-primary school.
- It was received by South Dublin County Council on 26 May 2021.
- Status: Granted on appeal 14 Feb 2022 (Decision to grant 20 Jul 2021 by the council).
Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Dublin 24 · Planning applications in Co. Dublin
Council register
The council's register shows: Decision to grant on 20 Jul 2021.
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Temporary two storey post-primary school
Provision of a temporary two storey post-primary school (Firhouse Educate Together Secondary School: Roll No. 68307J), comprising 10 classrooms and 3 specialist classrooms including all ancillary teacher and pupil facilities (2,000sq.m. gross floor area approximately); provision of an internal vehicular drop-off area and internal circulation routes; 15 surface parking spaces; bicycle parking; ball courts and play areas; access to the proposed temporary school will be from Oldcourt Road; provision of piped infrastructure and ducting; plant; pedestrian access points; ESB substation; attenuation tank; landscaping and boundary treatments; ancillary ramps and stairs; signage; changes in level and all associated site development and excavation works above and below ground; on a 0.86ha site approximately, which forms part of a larger 1.77ha landholding earmarked to accommodate a future permanent post-primary school; temporary permission for a period of 5 years is being sought.
- Location
- Dublin 24, Co. Dublin Map
- Council
- South Dublin County Council
- Planning reference
- SD21A/0137
Numbers and dates
- Floor area
- 2,004 m²
- Project type
- Public / civic
- Received
- 26 May 2021
- Council decision
- 20 Jul 2021
- Appeal lodged
- 16 Aug 2021
- Granted on appeal
- 14 Feb 2022
- Site start notified
- 1 May 2023
Timeline
- Application received
- Decision to grant by the council
- Appeal lodged
- Appeal decidedGrant permission with revised conditions
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file SD21A/0137 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
- AppealGrant permission with revised conditions · 311141 / 14 Feb 2022View the appeal record
How we know this
From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 1 May 2023Notice filed · Single story temporary school block 3 for Firhouse Educate Together Secondary School...View the site start
- Completion certificate recordedRecorded in May 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.