Energy · Co. Dublin
Profile Park, Baldonnel, Dublin 22
Granted 19 Jul 2022 (final grant issued 30 Aug 2022)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 22 by email
Key facts
- Planning application SD21A/0167 at Profile Park, Baldonnel, Dublin 22: Gas fired power plant with an electrical output of up to 125MW…
- It was received by South Dublin County Council on 25 May 2022.
- Status: Granted 19 Jul 2022 (final grant issued 30 Aug 2022).
- Work was due to start on 4 Apr 2023, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Dublin 22 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 19 Jul 2022.
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Gas fired power plant with an electrical output of up to 125MW…
Construction of a gas fired power plant with an electrical output of up to 125MW with associated balance of plant, equipment and buildings including; an Engine Hall building with a height of 18.9m, comprising 6 gas engines and ancillary infrastructure; an Electrical Annex Building with a height of 18.7m; a Workshop building with a height of 5. 1m; a Tank Farm building with a height of 5.68m; a Security hut with a height of 3.27m; an Exhaust Stack with a height of 31.8m; a Gas AGI including a kiosk with height of 3.3m; Radiator Coolers with a height of 8.46m; 2 electrical transformers with a height of 4.98m; Tanks including 2 x Diesel Oil Storage Tanks (volume of 2500m3 combined); SCR Urea Tank (26m3); Lube Oil Storage Tank (26m3); Lube Oil Maintenance Tank (26m3); Pilot Oil Tank (26m3); Fire Water Storage Tank (1000m3); Effluent Collecting Tank (26m3); Underground Surface Water Attenuation Tank (490m3); 2 new access onto the existing private road network with Profile Park; 12 parking spaces, footpaths, landscaping; fencing and all other associated site development plant and equipment and other works including surface water and foul wastewater drainage. An EIAR was submitted with this application.
- Location
- Dublin 22, Co. Dublin Map
- Council
- South Dublin County Council
- Planning reference
- SD21A/0167
Numbers and dates
- Floor area
- 2,741 m²
- Project type
- Energy
- Received
- 25 May 2022
- Decision to grant
- 19 Jul 2022
- Final grant
- 30 Aug 2022
- Site start notified
- 4 Apr 2023
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file SD21A/0167 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 4 Apr 2023Notice filed · phase 1 · Single storey engine hall and two storey electrical annex over cable basement.View the site start
- 30 Jun 2023Notice filed · phase 2 · Single storey tank farm building.View the site start
- 30 Jun 2023Notice filed · phase 3 · Single storey workshop and staff changing building.View the site start
- 1 Feb 2024Notice filed · phase 4 · Single storey security hutView the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.