Large residential · Co. Dublin

Gordon Park, Old Naas Road, Kingswood, Dublin 22

Granted 19 May 2022 (final grant issued 30 Jun 2022)

We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 22 by email

Key facts

  • Planning application SD21A/0327 at Gordon Park, Old Naas Road, Kingswood, Dublin 22: 77 homes.
  • It was received by South Dublin County Council on 22 Apr 2022.
  • Status: Granted 19 May 2022 (final grant issued 30 Jun 2022).

Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Dublin 22 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 19 May 2022.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

77 homes

A residential development of 77 dwellings comprised of 63 two storey houses and 14 apartments & duplex units accommodated in one 3 storey building. The proposed houses are comprised of 8 two bed houses & 55 three bed houses; the proposed apartments & duplex units are comprised of 7 one bed apartments at ground floor & 7 three bed duplex units overhead. The proposed development also provides for all associated site development & infrastructural works, car & bicycle parking, open spaces, hard & soft landscaping, boundary treatments and bin & bicycle storage; access to the development will be via a new vehicular entrance at the south-west corner of the site off the Old Naas Road. Permission is also sought to demolish the existing building on site approximately 455sq.m. all on a site area of 2.28Ha, at Gordon Park, Old Naas Road, Kingswood, Dublin 22 bounded to the west by the Old Nass Road, to the south by the Silken Park development and is located in the townland of Brownsbarn.

Location
Dublin 22, Co. Dublin Map
Planning reference
SD21A/0327

Numbers and dates

Homes
77
Floor area
8,192 m²
Estimated construction value
€14m to €26mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Large residential
Received
22 Apr 2022
Decision to grant
19 May 2022
Final grant
30 Jun 2022
Site start notified
30 Nov 2022

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Site history

This site's history

  1. Application SD26A/0222W at the same address: received 18 Sep 2026, no decision recorded yet.

    Change of use from a permitted ground floor café unit, [under Planning Ref. SD23A/0016], to proposed residential use in the form of a… Same address

Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.

Outlook

What happens next

Work packages named so far

  • Roads and site development worksNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file SD21A/0327 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file

How we know this

From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 30 Nov 2022Notice filed · phase 1 · At plot nos. 1-7, Gordon Park, Old Naas Road, Kingswood, Dublin 22, the construction of...View the site start
  2. 15 Mar 2023Notice filed · phase 2 · At 2-14(even), 15-30(incl.) & 32-42(even) Gordon Park, Kingswood Cross, Dublin 22, the...View the site start
  3. 16 Oct 2023Notice filed · phase 3 · At 31-41(odd), 43-57 (incl.) & 59-69(odd) Páirc Gordon, Old Naas Road, Kingswood, Dublin...View the site start
  4. Completion certificate recordedRecorded in Nov 2022 · 7 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
  5. Completion certificate recordedRecorded in Mar 2023 · 8 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
  6. Completion certificate recordedRecorded in Mar 2023 · 9 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 22

Get alerts for Dublin 22Free. We email you when new applications appear.

Free email alerts

Get new Dublin 22 projects by email

New applications, decisions and site starts in Dublin 22, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options