Commercial new build · Co. Dublin

Grange Castle Business Park, Clondalkin, Dublin 22

Granted 18 Jul 2022 (final grant issued 30 Aug 2022)

We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 22 by email

Key facts

  • Planning application SD22A/0148 at Grange Castle Business Park, Clondalkin, Dublin 22: 1 screened bin compound to be relocated to the south-east corner…
  • It was received by South Dublin County Council on 23 May 2022.
  • Status: Granted 18 Jul 2022 (final grant issued 30 Aug 2022).

Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Dublin 22 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 18 Jul 2022.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

1 screened bin compound to be relocated to the south-east corner…

1 screened bin compound to be relocated to the south-east corner of the site; 2 transformers within individual compounds and adjoining switch room (35.2sq.m) to be located to the east of the permitted data centre to replace screened transformer compound permitted to the south-east of the site; 1 new plantroom (19.8sq.m) and 1 water storage tank to be located to the west of the permitted data centre to replace previously approved fire suppression enclosure and new double gates to replace sliding gates at entrance into the permitted data centre site.

Location
Dublin 22, Co. Dublin Map
Planning reference
SD22A/0148

Numbers and dates

Floor area
55 m²
Project type
Commercial new build
Received
23 May 2022
Decision to grant
18 Jul 2022
Final grant
30 Aug 2022
Site start notified
3 Nov 2022

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Documents and evidence

Check the record

  • Council planning fileThe application file SD22A/0148 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file

How we know this

From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 3 Nov 2022Notice filed · Switchroom & Transformer Building at Data Centre Site INXDUB4, Construction of a single...View the site start
  2. Completion certificate recordedRecorded in Nov 2022 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 22

Get alerts for Dublin 22Free. We email you when new applications appear.

Free email alerts

Get new Dublin 22 projects by email

New applications, decisions and site starts in Dublin 22, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options