  • Planning application SD23A/0158 at 3-4, Crag Avenue, Clondalkin Industrial Estate, Clondalkin, Dublin 22: Alterations to the development permitted under Reg. Ref.
  • It was received by South Dublin County Council on 12 Jul 2023.
  • Status: Granted 5 Dec 2023.

Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Dublin 22 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 5 Dec 2023.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Alterations to the development permitted under Reg. Ref

Alterations to the development permitted under Reg. Ref.: SD18A/0068, as previously amended under Reg. Ref.: SD19A/0185 and Reg. Ref.: SD20A/0242, and to the development permitted under Reg. Ref.: SD20A/0309, as previously amended under Reg. Ref.: SD22A/0093. The proposed alterations in summary comprise the provision of an altered energy centre design and all associated development, along with minor alterations to the permitted site layout, provision of a gas AGI, and all ancillary works. The development, for which a 5-year planning permission is sought, will comprise the following: Construction of a revised energy centre in the western part of the subject site, to accommodate alternate generation technology, including 10 no. gas generation turbines (all with associated flues, 8 no. c. 33 metres (m) in height and 2 no. c. 15 m in height), 2 no. steam turbines including 2 no. steam turbine generator enclosure buildings with a gross floor area (GFA) of 219 sq.m each and a height of c. 6.2 m, associated steam turbine generator distribution and control structure with a GFA of 84 sq.m and an overall height of c. 4.2 m, and 2 no. steam turbine / air cooled condenser structures with a height of c. 25.4 m. Construction of 8 no. 33/20kV transformer bays to the southeast of the energy centre, with a further 12 no. gas / steam transformers to serve the proposed turbines to the west of the energy centre. Provision of 3 no. 13.6 m high fuel storage tanks, a fuel oil enclosure building (with a GFA of 50 sq.m and an overall height of c. 3.8m), a fire pump enclosure building (with a GFA of 65 sq.m and an overall height of c. 3.2 m) along with 3 no. c. 14.1 m high sprinkler tanks, a c. 14.5 m high water tank, and a water treatment plant building (with a GFA of 218 sq.m and a maximum height of c. 17 m including rooftop plant). Provision of 6 no. black-start / emergency generators to the south of the energy centre with an overall height of c. 5 m; Provision of a single storey over basement level powertrunk building (with a GFA of 932 sq.m and an overall height of c. 4.1 m) to the southeast of the proposed energy centre. Provision of a 3-storey over basement medium voltage / low voltage building (with a GFA of 3,161 sq.m and an overall height of c. 16.3 m) to the southwest of the proposed energy centre. Provision of 2 no. transformers adjacent to the substation constructed under Reg. Ref.: SD18A/0068, as amended by Reg. Ref.: SD19A/0185 (located to the southwest of the proposed energy centre). Provision of a guard hut with a GFA of 21 sq.m and with a height of c. 3.2m, to the west of the medium voltage / low voltage building. Provision of a Gas AGI (above-ground installation) to the southwest of the subject site within a fenced compound, accommodating a single storey control room building with a GFA of 10 sq.m and overall height of c. 3 m, a plant kiosk with a GFA of 17 sq.m and an overall height of c. 3 m, and a boiler house with a GFA of 13 sq.m and an overall height of c. 3m. Reorientation of permitted ICT Facility Building No. 4 to accommodate the revised energy centre layout (with no other change to this permitted building). Associated and ancillary alterations to the site layout relating to landscaping, parking (including 18 no. car parking spaces, and bicycle parking within a covered bicycle shelter to serve the energy centre) and roads layouts, lighting and services, boundary treatments, drainage, landscaping, and all associated and ancillary works. An Environmental Impact Assessment Report (EIAR) will be submitted to the Planning Authority with the planning application and the EIAR will be available for inspection or purchase at a fee not exceeding the reasonable cost of making a copy at the offices of the Planning Authority. An EPA-Industrial Emissions Directive (IE) licence will be applied for to facilitate the operation of the proposed development.

Location
Dublin 22, Co. Dublin Map
Planning reference
SD23A/0158

Numbers and dates

Floor area
5,009 m²
Project type
Infrastructure
Received
12 Jul 2023
Granted
5 Dec 2023
Site start
29 Jan 2024

Timeline

  1. Application received
  2. Granted
  3. Appeal decidedAppeal withdrawn S.140(1)(a)
  4. Site start

Site history

This site's history

  1. Earlier permission SD18A/0068 for this site: granted 17 Dec 2018.

    Alterations to approved plans (Grant of Permission ref PL06S.243151 and PA Reg Ref SD13A/0271) consisting of the following to be… Named in this application's description
  2. Earlier permission SD19A/0185 for this site: granted 31 Jul 2019.

    Alterations to approved plans (Grant of Permission ref PL06S.243151 and PA Reg Ref SD13A/0271 and SD18A/0068) to the previously granted… Named in this application's description
  3. Earlier permission SD20A/0242 for this site: granted 6 Jan 2021.

    The provision of alternate entrance and access arrangements from Crag Avenue to serve the permitted data storage centre, energy centre and… Named in this application's description
  4. Earlier permission SD20A/0309 for this site: granted 23 Mar 2021.

    Provision of 4 new information and communications technology (ICT) Facility buildings and associated development at the subject site… Named in this application's description
  5. Earlier permission SD22A/0093 for this site: granted 20 Jul 2022.

    Amendments to the development permitted under Reg. Ref. SD20A/0309 comprising: alterations to permitted ICT Facility buildings 2 and 3, to… Named in this application's description

Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.

Outlook

What happens next

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description
  • Basement parkingNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

How we know this

From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 29 Jan 2024Work started · phase 1 · It is proposed to construct an electrical plant building located on the DUB 10 Data...View the site start
  2. 8 Mar 2024Work started · phase 2 · A four-storey electrical building is proposed to be built in DUB 10 Data Campus area...View the site start
  3. 24 Sep 2024Work started · phase 3 · Development of an Above Ground Installation (AGI) within the Crag Digital Ltd. premises...View the site start
  4. Completion certificate recordedRecorded in Jan 2024 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 26 Oct 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 22

Get alerts for Dublin 22Free. We email you when new applications appear.

Free email alerts

Get new Dublin 22 projects by email

New applications, decisions and site starts in Dublin 22, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options