~86 dwellings, Cookstown House, Cookstown Way, Tallaght, Dublin 24. - Planning Application SD25A/0207W
Dublin / Dublin 24 / Cookstown House, Cookstown Way, Tallaght, Dublin 24.
Source-linked planning record
~86 dwellings, Cookstown House, Cookstown Way, Tallaght, Dublin 24. - Planning Application SD25A/0207W
Dublin / Dublin 24 / Cookstown House, Cookstown Way, Tallaght, Dublin 24.- PB ref
- PB-10000400385
- Plan ref
- SD25A/0207W
- Authority
- South Dublin County Council
- Stage / date
- Granted / 23 Oct 2025
- Est. value band
- Value not disclosed
- Units / floor
- 86 / 382 m²
- Project class
- Mixed use
- Promoter
- not included in reference feed
- Architect / agent
- not included in reference feed
Source: https://planning.agileapplications.ie/southdublin/application-details/68848
Key facts
Lead summary
- Source
- South Dublin County Council public planning register
- Planning authority
- South Dublin County Council
- Application reference
- SD25A/0207W
- Applicant
- not included in reference feed
- Agent
- not included in reference feed
- Decision stage
- Granted
- Decision
- 23 Oct 2025
- Units
- 86
- Floor area
- 382 m²
Official description
Verbatim source text
We, KAVCO C TOWN PROJECT LIMITED, intend to apply for planning permission for the proposed development at the site, Cookstown House, Cookstown Way, Tallaght, Dublin 24. The proposed development consists of the following: modifications of the previously approved application SDCC Reg. Ref. SD23A/0237. The proposed modifications include a revised Ground-floor layout to convert the previous commercial unit, the adjacent refuse store and part of the previous communal amenity space into an additional 6 no. residential units as follows; 1 no. studio unit, 3 no. one-bedroom units and 2 no. two-bedroom units. The proposed changes will increase the total number of apartments from 80 no. units to 86 no. units. A recessed balcony has been provided to each of the proposed apartments. Minor modifications are to be made to the elevations at ground floor level only. There are no changes proposed to the height of the building. All with associated site works, bin and bicycle storage.
Verify against official sourceProject team
Named source parties
- Promoter
- not included in reference feed
- Planning agent
- not included in reference feed
Lifecycle timeline
Application to site progress
-
Completed
Completion not recorded Smaller works often do not require a completion certificate.
Likely trades & supplier leads