Planning record · Co. Dublin
9, Tullyhall Green, Lucan, Co. Dublin, K78 CP59
Granted 24 Nov 2025 (final grant issued 15 Jan 2026)
Key facts
- Planning application SD25B/0606W at 9, Tullyhall Green, Lucan, Co. Dublin, K78 CP59: Attic conversion with dormer window to the rear.
- It was received by South Dublin County Council on 17 Oct 2025.
- Status: Granted 24 Nov 2025 (final grant issued 15 Jan 2026).
- Work started on site on 6 Mar 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the South Dublin County Council planning register, checked 2 Jun 2026. Open the council's file
More planning applications in Lucan · Planning applications in Co. Dublin
What and where
Attic conversion with dormer window to the rear
Attic conversion with dormer window to the rear. Flat-roof porch extension to the front. Single-storey flat-roof extension to the rear. Installation of two garden rooms to the rear of the property with a pergola linking both.
- Location
- Lucan, Co. Dublin Map
- Council
- South Dublin County Council
- Planning reference
- SD25B/0606W
Numbers and dates
- Floor area
- 32 m²
- Project type
- Planning record
- Received
- 17 Oct 2025
- Decision to grant
- 24 Nov 2025
- Final grant
- 15 Jan 2026
- Site start
- 6 Mar 2026
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file SD25B/0606W on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the South Dublin County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.
Site starts
Commencement notices for this permission
- 6 Mar 2026Work started · Attic conversion with dormer window to the rear. Flat-roof porch extension to the front...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.