Final permission issued on 19 August for a 739 m² ancillary industrial building within the existing Citywest premises. The reviewed documents do not establish commencement or completion.
Final grant defines a 739 m² steel-frame industrial building
Granted industrial building and envelope description
What the evidence says
The 19 August final grant describes a physically separate building ancillary to the existing premises, with a steel portal frame, insulated composite roof panels and horizontal metal wall panels. It sets the parapet at 110.65 m OD, about 10.05 m above the yard, and specifies west and south roller doors.
Why it may matter — interpretation
Steelwork, cladding and door suppliers have a defined planning-stage package to qualify against construction details.
What is not established
Fabricator appointment, panel product selection, manufacture and installation are not established.
Inspect the evidence
Final grant including amended contribution condition · p.1
Final Grant 19-Aug-2026; 739 sq.m; steel portal frame · Issued 2026-08-19 · Final Grant Order 0765; decision 8 July; incorporates PR/0805/26 of 17 July · Checked 2026-09-07
Final Grant 19-Aug-2026; 739 sq.m; steel portal frame
Tree-pit drainage needs an agreed slope and inflow detail
Pre-commencement drainage condition and submitted response
What the evidence says
Condition 2 requires revised plan and cross sections showing how hardstanding runoff reaches tree pits, replacing the proposed 1:2 side slope with 1:3 or 1:4, or agreeing an alternative with Water Services. The July revision B submission shows two tree pits and runoff inlets; its presence does not prove council agreement.
Why it may matter — interpretation
Civil and landscape teams need the approved slope, inflow and overflow interface before constructing the tree-pit SuDS.
What is not established
Written acceptance of condition 2, installed attenuation and as-built drainage performance were not reviewed.
Inspect the evidence
Final grant including amended contribution condition · p.2
Condition 2: slope profile of 1:3 or 1:4 · Issued 2026-08-19 · Final Grant Order 0765; decision 8 July; incorporates PR/0805/26 of 17 July · Checked 2026-09-07
Condition 2: slope profile of 1:3 or 1:4
Submitted SuDS plan and tree-pit details · p.1
PROPOSED SUDS PLAN AND TREE PIT DETAILS; revision B · Issued 2026-07-20 · 25039-20-DR-0025 revision B; revised for planning 20 July; special-version stamp refers to original signatures · Checked 2026-09-07
PROPOSED SUDS PLAN AND TREE PIT DETAILS; revision B
All surface parking needs EV ducting; 20% needs initial chargers
Pre-commencement roads and electrical conditions
What the evidence says
Condition 8 requires ducting and termination points at all surface parking spaces and charging points at 20% initially. The EV design and signage, public lighting design and construction management plan require written agreement before development starts.
Why it may matter — interpretation
Electrical contractors need the agreed parking count and layout to turn the percentages into equipment quantities and cable routes.
What is not established
Charger counts, equipment make, agreed compliance details and installed charging infrastructure are not established.
Inspect the evidence
Final grant including amended contribution condition · p.3
Condition 8: 100% ducting; 20% charging points initially · Issued 2026-08-19 · Final Grant Order 0765; decision 8 July; incorporates PR/0805/26 of 17 July · Checked 2026-09-07
Condition 8: 100% ducting; 20% charging points initially
Crane use and vegetation protection affect the construction programme
Conditions governing site mobilisation and lifting
What the evidence says
Condition 7 requires crane operations to be coordinated with Air Corps air-traffic services at least 28 days before use. Conditions 5 and 6 require green-infrastructure details, hedgerow protection and an arboricultural method statement, with protection implemented before site works.
Why it may matter — interpretation
Steel erection and siteworks programmes need to allow for aviation coordination and vegetation-protection arrangements.
What is not established
Crane coordination, agreed protection plans and mobilisation are not established.
Inspect the evidence
Final grant including amended contribution condition · p.2
Conditions 5 and 6 · Issued 2026-08-19 · Final Grant Order 0765; decision 8 July; incorporates PR/0805/26 of 17 July · Checked 2026-09-07
Conditions 5 and 6
Final grant including amended contribution condition · p.3
Condition 7: no later than 28 days before use · Issued 2026-08-19 · Final Grant Order 0765; decision 8 July; incorporates PR/0805/26 of 17 July · Checked 2026-09-07
Condition 7: no later than 28 days before use
The amended condition uses 739 m² rather than the earlier 1,858 m² error
Final grant incorporates the July condition correction
What the evidence says
The final grant reproduces condition 18 and then expressly replaces it with the 17 July amendment: the contribution is 88,325.28 euro rather than the earlier 222,068.16 euro. This is a correction to the contribution calculation, not a larger industrial-building scope.
Why it may matter — interpretation
Commercial review should use the amended amount and the 739 m² development description when checking the permission.
What is not established
Payment, any later index adjustment and satisfaction of the financial condition are not established.
Inspect the evidence
Final grant including amended contribution condition · p.5
Earlier condition 18: 222,068.16 · Issued 2026-08-19 · Final Grant Order 0765; decision 8 July; incorporates PR/0805/26 of 17 July · Checked 2026-09-07
Earlier condition 18: 222,068.16
Final grant including amended contribution condition · p.6
Condition 18 was amended by PR/0805/26 on 17/07/2026: 88,325.28 · Issued 2026-08-19 · Final Grant Order 0765; decision 8 July; incorporates PR/0805/26 of 17 July · Checked 2026-09-07
Condition 18 was amended by PR/0805/26 on 17/07/2026: 88,325.28
Amended executive order correcting the contribution · p.2
Contribution corrected from 1858 m2 to 739 m2 · Issued 2026-07-17 · PR/0805/26 signed 17 July 2026 · Checked 2026-09-07
Contribution corrected from 1858 m2 to 739 m2
The declared pages of these government-published PDFs were visually inspected. Other catalogue files, later compliance, procurement and installed specifications were not established. Historical weekly membership is retained separately from these document dates.