Infrastructure · Co. Dublin

Site within Mountpark Grange Castle West, Gollierstown Road, Lucan, Co. Dublin

Granted 29 Jul 2026

Get updates on this application

We'll email you when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application SD26A/0132W at Site Within Mountpark Grange Castle West, Gollierstown Road, Lucan, Co. Dublin: Two logistics /warehousing units.
  • It was received by South Dublin County Council on 4 Jun 2026.
  • Status: Granted 29 Jul 2026.
  • Work was due to start on 28 Oct 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the South Dublin County Council planning register, checked 19 Aug 2026. Open the council's file

More planning applications in Lucan · Planning applications in Co. Dublin

What and where

Two logistics /warehousing units

The proposed development will consist of: The construction of two logistics /warehousing units (Units 5a and 5b) with associated office accommodation, service yards, ancillary structures/areas, and substation with two switch rooms. The overall floor area of the proposed logistics /warehousing units is c. 12,191.9 sq.m (Gross Internal Area (GIA)) with a total of c. 922.1 sq.m of office space. See following breakdown of each unit: o Unit 5a will comprise GIA c. 8,255.5 sq.m (including c. 635.8 sq.m of associated office space) and measures c. 17.6m from finished floor level (FFL) to roof ridge; o Unit 5b will comprise GIA c. 3,936.4 sq.m (including c. 286.3 sq.m of associated office space) and measures c. 15.2m from FFL to roof ridge; Access to the units will be from the existing internal link road. Some minor works will be required to the existing link road to accommodate the proposed units, including relocation of speed ramp and two new pedestrian crossings; The provision of rain gardens across the site; Provision of no. 86 car parking spaces and 60 bicycle spaces to serve the proposed development; The installation of a padel court and; All ancillary landscaping, boundary treatments, associated infrastructure, and site development works to support the development.

Location
Lucan, Co. Dublin Map
Planning reference
SD26A/0132W

Numbers and dates

Floor area
12,192 m²
Project type
Infrastructure
Received
4 Jun 2026
Granted
29 Jul 2026
Site start notified
28 Oct 2026

Timeline

  1. Application received
  2. Granted
  3. Site start notified

Site history

This site's history

  1. Application SD26A/0210W at the same address: received 31 Aug 2026, no decision recorded yet.

    The construction of a logistics /warehousing unit (Unit 6) with associated office and welfare accommodation, service yards, ancillary… Same address

Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.

Outlook

What happens next

Work was due to start on 28 Oct 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file SD26A/0132W on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file

Reviewed build intelligence

What the documents establish

Government document review

Council decision to grant 29 July 2026, notified 30 July. Selected document is not a final grant; later finish and lighting agreements remain unverified.

3 official documents inspected · Checked 2026-09-06 · Official file index

Office heating uses ASHP; heat-recovery ventilation has two options

Application design; later agreement and installation unverified · Office/front-of-house heating and the report's ventilation options for Units 5A and 5B

What the evidence says
The Issue 02 energy statement proposes all-electric air-source heat pumps for heating and cooling office spaces and front-of-house areas. The next section lists local heat-recovery ventilation units or central 100% outside-air AHUs with heat recovery, and variable-speed fan drives suitable for future demand-controlled operation. The office heating scope is not extended to all warehouse space, and the illustrative equipment photographs do not select a manufacturer.

Why it may matter — interpretation
An HVAC designer or supplier should confirm the office loads and chosen local-versus-central ventilation arrangement before selecting equipment or pricing the package.

What is not established
Final capacities, chosen ventilation option, selected manufacturer, refrigerant schedule and installation are unverified.

Inspect the evidence

Energy Efficiency and Climate Change Adaptation Design Statement · p.27
office spaces and front-of-house areas · Issued 2026-06-03 · Issue 02, Design Team Review, received 4 June 2026. The recurring 8 July 2021 header is the standard report template date, not this project revision. · Checked 2026-09-06

office spaces and front-of-house areas

Energy Efficiency and Climate Change Adaptation Design Statement · p.28
Local Heat Recovery · Issued 2026-06-03 · Issue 02, Design Team Review, received 4 June 2026. The recurring 8 July 2021 header is the standard report template date, not this project revision. · Checked 2026-09-06

Local Heat Recovery

Roof PV is proposed for both logistics units

Application design; later agreement and installation unverified · Designated roof areas of Units 5A and 5B under SD26A/0132W

What the evidence says
The energy statement proposes rooftop photovoltaic systems in designated roof areas for Units 5A and 5B. It describes arrays optimised towards a minimum BER A design target and says excess power has the potential to be fed to the grid. These are the applicant's design intentions, not a measured BER, approved export connection or installed array.

Why it may matter — interpretation
A solar contractor can identify a roof-array package and should seek the final layout, structural coordination, capacity and connection agreement before pricing.

What is not established
Panel count, rated capacity, manufacturer, final roof layout, export agreement, procurement and installation are not established.

Inspect the evidence

Energy Efficiency and Climate Change Adaptation Design Statement · p.31
at roof level · Issued 2026-06-03 · Issue 02, Design Team Review, received 4 June 2026. The recurring 8 July 2021 header is the standard report template date, not this project revision. · Checked 2026-09-06

at roof level

A BEMS is proposed for both units

Application design; later agreement and installation unverified · Controls and metering proposal for Units 5A and 5B

What the evidence says
The energy statement proposes a Building Energy Management System with front-end software to control and monitor mechanical and electrical services in Units 5A and 5B and provide metering information to facilities management. It does not identify a vendor or an installed system.

Why it may matter — interpretation
A controls integrator should request the points schedule, plant interfaces and metering requirements before specifying the proposed BEMS.

What is not established
Vendor, communications protocols, approved controls sequence, points schedule, procurement and commissioned system are unverified.

Inspect the evidence

Energy Efficiency and Climate Change Adaptation Design Statement · p.31
Building Energy Management System · Issued 2026-06-03 · Issue 02, Design Team Review, received 4 June 2026. The recurring 8 July 2021 header is the standard report template date, not this project revision. · Checked 2026-09-06

Building Energy Management System

Office and warehouse fabric targets are different

Application design; later agreement and installation unverified · Separate office, warehouse-panel and dock-door elements in the application energy statement

What the evidence says
The Issue 02 energy statement sets proposed roof U-values of at most 0.14 W/m²K for offices and 0.16 for warehouses. Wall targets are 0.15 for offices, 0.18 for warehouse RW panels and 0.15 for warehouse AWP panels. The same table targets dock-door U-values of at most 1.30 W/m²K. These are design targets for specified elements, not measured building performance or a selected panel product.

Why it may matter — interpretation
An envelope or dock-door supplier needs to match the relevant element target, then coordinate the later council finish approval rather than applying one fabric value across the whole scheme.

What is not established
Exact panel build-ups, products, certified installed performance and final council finish agreement are not verified.

Inspect the evidence

Energy Efficiency and Climate Change Adaptation Design Statement · p.24
Minimum Required Passive Performance · Issued 2026-06-03 · Issue 02, Design Team Review, received 4 June 2026. The recurring 8 July 2021 header is the standard report template date, not this project revision. · Checked 2026-09-06

Minimum Required Passive Performance

Phase 2 uses the wider drainage network and proposes full-retention interceptors

Application design; later agreement and installation unverified · Phase 2 connections and treatment measures; wider Phase 1 catchment infrastructure remains separate

What the evidence says
The engineering report places Units 5A and 5B in the wider permitted Phase 1 Outfall 2 catchment. It proposes siphonic roof drainage, permeable paving, filter drains, tree pits and rain gardens discharging to the wider attenuation system. Service-yard runoff is to pass through Class 1 full-retention interceptors, and fire-tender routes use Grasscrete or a similar approved surface. The wider catchment's basin volume is not a new Phase 2 construction quantity.

Why it may matter — interpretation
A civil or interceptor supplier should establish the Phase 2 connection and treatment package against the existing-network interface before pricing new storage or pipework.

What is not established
The report table shows 92.6 l/s while adjacent Phase 2 prose states 92.4 l/s for the shared outfall; this requires design clarification. Final interceptor models, compliance drawings and the actual built network have not been independently verified.

Inspect the evidence

Engineering Planning Report and Flood Risk Assessment: Phase 2 · p.7
Phase 2 · Issued 2026-05-21 · Report footers 21 May 2026; control table separately gives PL1 31 March 2026. Received 4 June 2026; both issue indicators retained. · Checked 2026-09-06

Phase 2

Engineering Planning Report and Flood Risk Assessment: Phase 2 · p.9
Class 1 full retention interceptors · Issued 2026-05-21 · Report footers 21 May 2026; control table separately gives PL1 31 March 2026. Received 4 June 2026; both issue indicators retained. · Checked 2026-09-06

Class 1 full retention interceptors

The decision requires revised lighting evidence before commencement

Council decision condition; final agreement unverified · Condition 3 for external and padel-court lighting under SD26A/0132W

What the evidence says
Condition 3 of the council decision requires written agreement to revised lighting information, including horizontal and vertical levels where bats are present, spill values at the Canal, existing lighting and proposed changes, and padel-court spill affecting Lucan/Tobermaclugg Stream. The decision date is 29 July 2026; the notification is signed 30 July. This is not a final lighting approval.

Why it may matter — interpretation
A lighting designer must coordinate ecological constraints and the requested spill calculations before relying on the original lighting layout.

What is not established
The written agreement, revised calculations, final luminaire schedule and installed lighting are not established.

Inspect the evidence

Notification of decision to grant permission · p.2
Lighting · Issued 2026-07-30 · Decision order 29 July 2026; signed notification and catalogue label 30 July. Final grant not established. · Checked 2026-09-06

Lighting

Notification of decision to grant permission · p.3
light levels · Issued 2026-07-30 · Decision order 29 July 2026; signed notification and catalogue label 30 July. Final grant not established. · Checked 2026-09-06

light levels

Unit 5B office elevations and finishes need written agreement

Council decision condition; final agreement unverified · Condition 2: all building finishes, with a specific revised-elevation requirement for Unit 5B offices

What the evidence says
Condition 2 requires details of external materials and finishes for all permitted buildings and revised elevations for the Unit 5B office block, using a more varied material or colour scheme to break up its massing. These submissions must be agreed in writing before commencement. The selected notification records a decision to grant, not a final grant or a completed condition agreement.

Why it may matter — interpretation
A façade designer or supplier should obtain the agreed revised elevation and colour/material schedule before fixing quantities or ordering finishes for Unit 5B.

What is not established
The revised approved elevations, chosen finish products, final grant, procurement and installation are unverified.

Inspect the evidence

Notification of decision to grant permission · p.1
SD26A/0132W · Issued 2026-07-30 · Decision order 29 July 2026; signed notification and catalogue label 30 July. Final grant not established. · Checked 2026-09-06

SD26A/0132W

Notification of decision to grant permission · p.2
external materials and finishes · Issued 2026-07-30 · Decision order 29 July 2026; signed notification and catalogue label 30 July. Final grant not established. · Checked 2026-09-06

external materials and finishes
Remaining document questions
  • Which later official decision, approved detail or revision changes these source-specific findings?
  • Has a phase-specific official record established the selected equipment or installed specification?

Selected pages of 3 government-published PDFs were visually inspected. Three selected PDFs and fifteen supporting pages were inspected from the exact 90-document catalogue; the whole catalogue and later compliance material were not reviewed. Proposals do not establish procurement or installed work.

How we know this

From the South Dublin County Council planning register, checked 19 Aug 2026. We link to the council's own file so you can check the official record before you act. Facts from the planning documents were read from the documents in that file.

Site starts

Commencement notices for this permission

  1. 28 Oct 2026Notice filed · Construction of a new standalone ESB substation with two customer switch rooms at Units...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Lucan

Get alerts for LucanFree. We email you when new applications appear.

Free email alerts

Get new Lucan projects by email

New applications, decisions and site starts in Lucan, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options