Large residential · Co. Dublin

Adamstown, Lucan, Co. Dublin

Granted 22 Jun 2020

We no longer update this application, so we can't email you about it. Get new planning applications in Lucan by email

Key facts

  • Planning application SDZ19A/0011 at Adamstown, Lucan, Co. Dublin: 245 homes.
  • It was received by South Dublin County Council on 24 Apr 2020.
  • Status: Granted 22 Jun 2020.

Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Lucan · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 22 Jun 2020.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

245 homes

245 dwellings (up to a maximum of c. 23,903.5sq.m. GFA) in a mixture of terraced and detached houses, duplexes and apartments as follows: 214 houses shall consist of 169 two storey three bedroom houses, 68 with the option of a single storey rear extension at ground floor level (house type B1x and B2x); 45 three storey four bedroom houses; 15 apartment units shall be accommodated in 1 block of five storeys (Block 01) to consist of 2 one bed apartments and 13 two bed apartments; 16 duplexes shall be accommodated in 1 block of three storeys (Block 02) to contain 8 one storey two bed units and 8 two storey three bed units; the provision of 1.24 Ha of public open space; provision of 370 car parking spaces; provision of a pedestrian (toucan) crossing over Adamstown Park, linking the site to Tandy's Lane Park and raised pedestrian crossing over the re-aligned Tandy's Lane, linking the site to the St. Helen's Development Area; all ancillary and associated site development and landscape works; vehicular access to serve the development is to be provided in a number of locations off Adamstown Park (2), Adamstown Drive (4 opened to traffic as part of this phase of development and 1 additional access closed to traffic until future phase of development to be used for construction access) and off the re-aligned Tandy's Lane (1) in the townlands of Dodsboro and Finnstown, bounded generally to the north by the Adamstown Drive, to the east by Adamstown Park and a site of a future Primary School, to the south by the re-aligned Tandy's Lane and part of the undeveloped Tandy's Lane Village Development Area, and to the west part of the undeveloped remainder of the Tandy's Lane Village Development Area in accordance with the Adamstown Planning Scheme 2014, as amended and relates to a proposed development within the Adamstown Strategic Development Zone Planning Scheme Area as defined by Statutory Instrument No. 272 of 2001.

Location
Lucan, Co. Dublin Map
Planning reference
SDZ19A/0011

Numbers and dates

Homes
245
Floor area
23,904 m²
Estimated construction value
€41m to €75mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Large residential
Received
24 Apr 2020
Granted
22 Jun 2020
Site start notified
14 May 2021

Timeline

  1. Application received
  2. Granted
  3. Site start notified

Documents and evidence

Check the record

  • Council planning fileThe application file SDZ19A/0011 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file

How we know this

From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 14 May 2021Notice filed · phase 1 · At Tandy's Lane Village, the construction of 214 no. houses with 208 in terraces and 6...View the site start
  2. 7 Mar 2022Notice filed · phase 2 · At 1-15 Tandy's House, Tandy's Lane, Adamstown, Lucan, Co. Dublin, the construction of...View the site start
  3. 25 Apr 2022Notice filed · phase 3 · At 1-16 Tandy's Plaza, Tandy's Lane, Adamstown, Lucan, Co. Dublin, the construction of 8...View the site start
  4. Completion certificate recordedRecorded in May 2021 · 12 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
  5. Completion certificate recordedRecorded in May 2021 · 32 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
  6. Completion certificate recordedRecorded in May 2021 · 6 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Lucan

Get alerts for LucanFree. We email you when new applications appear.

Free email alerts

Get new Lucan projects by email

New applications, decisions and site starts in Lucan, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options