Large residential · Co. Dublin
Within the Townlands of Cappagh, Clonburris Little & Kishoge, Co. Dublin
Granted 23 Aug 2022
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Dublin by email
Key facts
- Planning application SDZ21A/0022 at Within The Townlands of Cappagh, Clonburris Little & Kishoge, Co. Dublin: 569 homes.
- It was received by South Dublin County Council on 29 Jun 2022.
- Status: Granted 23 Aug 2022.
Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file
Council register
The council's register shows: Granted on 23 Aug 2022.
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
569 homes
The construction of 569 dwellings, a creche, innovation hub and open space in the Clonburris South West Development Area of the Clonburris SDZ Planning Scheme 2019 as follows: 173 houses comprising 8 two bedroom houses, 153 three bedroom houses and 12 four bedroom houses (147 dwellings in CSW-S4 consisting of 8 two bedroom houses, 127 three bedroom houses & 12 four bedroom houses & 26 three bedroom dwellings in CSW-S3}, all 2 storey comprising semi-detached, terraced, end terrace units (with parking and private open space); (B) 148 duplex apartments/apartments {88 in CSW-S4 & 60 in CSW-S3) comprising 74 two bedroom units and 74 three bedroom units, in 16 three storey buildings. In CSW-S4 Duplex Blocks A, B, C, D, E, F, G, J, K, comprise 8 units (4 two bed & 4 three bed units), Duplex Block H comprises 16 units (8 two bed & 8 three bed units), In CSW-S3 Blocks L, N & O comprise 8 units (4 two bed & 4 three bed units), Block M comprises 14 units (7 two bed & 7 three bed units), Block P comprises 10 units (5 two bed & 5 three bed units), Block Q comprises 12 units {6 two bed & 6 three bed units), all to have terraces/pitched roof; (C) 396 apartments as follows: within CSW-S4, Block 1 consists of 172 apartments (76 one bedroom, 91 two bedroom and 5 three bedroom apartments), in a 2-building arrangement both 6 storeys in height. Within CSW-S3, Block 2 {4 storeys) comprises 16 one bedroom apartments and 22 two bedroom apartments, Block 3 (4 storeys) comprises 16 one bedroom apartments and 22 two bedroom apartments (all apartments to have terrace or balcony); (D) Provision of an innovation hub (626sq.m) and creche (c. 547sq.m) in a part 3/4 storey 'local node' building in CSWS4; (E) Vehicular access will be from the permitted Clonburris Southern Link Street (SDZ20A/0021) and R113 to the east {along with provision of internal haul routes {for construction) to connect to the R136 to the west); (F) Public Open Space/landscaping of c. 4.1 hectares (to include Local Park and MUGA in CSW-S3, Grand Canal Park, along the southern and eastern boundaries of the site to connect to existing Grand Canal towpath) as well as a series of communal open spaces to serve apartments and duplex units (c. 0.39 ha); (G) all ancillary development works including footpaths, landscaping boundary treatments, public, private open space areas, car parking (656 spaces) and bicycle parking (672 spaces), single storey ESB substations/bike/bin stores, 'Gateway' entrance signage (2), solar panels at roof level of apartments, and all ancillary site development/construction works; (H) Permission is also sought for revisions to attenuation permitted under SDZ20A/0021 as well as connection to water supply, and provision of foul drainage infrastructure; this application is being made in accordance with the Clonburris Strategic Development Zone Planning Scheme 2019 and relates to a proposed development within the Clonburris Strategic Development Planning Scheme Area, as defined by Statutory Instrument No. 604 of 2015; an Environmental Impact Assessment Report accompanies this planning application; the application applies for 7-year planning permission for development at this site of c. 17.02 hectares (on two parcels of land to include entrance area) within the townlands of Cappagh, Clonburris Little & Kishoge, Co. Dublin all on wider lands bounded generally by undeveloped lands and the Dublin-Cork railway line to the north, undeveloped lands and the Grand Canal to the south, the R113 {Fonthill Road) to the east and the R136 to the west.
- Location
- Clonburris Little & Kishoge, Co. Dublin Map
- Council
- South Dublin County Council
- Planning reference
- SDZ21A/0022
Numbers and dates
- Homes
- 569
- Floor area
- 37,472 m²
- Estimated construction value
- €65m to €120mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Large residential
- Received
- 29 Jun 2022
- Granted
- 23 Aug 2022
- Site start notified
- 30 Jan 2023
Timeline
- Application received
- Granted
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file SDZ21A/0022 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 30 Jan 2023Notice filed · phase 1 · Development consists of the construction of 145no dwelling houses and 3no Duplex Blocks...View the site start
- 13 Mar 2023Notice filed · phase 2 · Construction of a 4-storey multi use building as part of the Clonburris Phase 1a...View the site start
- 10 Apr 2023Notice filed · phase 3 · Development known as Duplex Block F, Phase 1a, Clonburris, consisting of the...View the site start
- 10 May 2023Notice filed · phase 4 · Development known as Duplex Block G, Phase 1a, Clonburris, consisting of the...View the site start
- 26 Jun 2023Notice filed · phase 5 · Development known as Duplex Block H, Phase 1a, Clonburris, consisting of the...View the site start
- 28 Jul 2023Notice filed · phase 6 · Development known as Duplex Block J, Phase 1a, Clonburris, consisting of the...View the site start
- 14 Aug 2023Notice filed · phase 7 · Construction of a 4-storey 38-unit apartment building including typical ancillary areas...View the site start
- 21 Aug 2023Notice filed · phase 8 · Bin Stores 1, 4 and 5. The construction of 3no. self- contained single- storey bin...View the site start
- 28 Aug 2023Notice filed · phase 9 · Block 3 - Construction of a 4-storey 38-unit apartment building including typical...View the site start
- 22 Sep 2023Notice filed · phase 10 · Development known as Duplex Block K, Phase 1a, Clonburris, consisting of the...View the site start
- 4 Oct 2023Notice filed · phase 11 · Development consists of the construction of 26no dwelling houses and 6no Duplex Blocks...View the site start
- Completion certificate recordedRecorded in Jan 2023 · 38 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Jan 2023 · 26 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Jan 2023 · 21 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.