Mixed use · Co. Dublin
Within the townland of Cappagh, Clonburris, Dublin 22
Granted 31 Oct 2023
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 22 by email
Key facts
- Planning application SDZ22A/0018 at Within The Townland of Cappagh, Clonburris, Dublin 22: Mixed-use development.
- It was received by South Dublin County Council on 6 Oct 2023.
- Status: Granted 31 Oct 2023.
Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Dublin 22 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 31 Oct 2023.
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Mixed-use development
Construction of a mixed-use development comprising 594 apartments, office floorspace, 4 retail units, a creche and urban square in the Clonburris Development Areas CUCS3 & CSWS3 of the Clonburris SDZ Planning Scheme 2019 as follows, 594 apartments (255 one bedroom apartments, 307 two bedroom apartments and 32 three bedroom apartments (all apartments to have terrace or balcony; ancillary communal amenity spaces for residents) as follows; Block A (4 and 6 storeys with undercroft) comprises 96 apartments consisting of 36 one bedroom apartments, 48 two bedroom apartments and 12 three bedroom apartments (with creche c. 609sq. m at ground and first floor as well as play area; Block B (6 storeys with undercroft) comprises 77 apartments consisting of 44 one bedroom apartments, 28 two room apartments and 5 three bedroom apartments; Block D (5 and 7 storeys with undercroft) comprises 71 apartments consisting of 39 one bedroom apartments and 32 two bedroom apartments; Block E (6 storeys with undercroft) comprises 100 apartments consisting of 47 one bedroom apartments, 48 two bedroom apartments and 5 three bedroom apartments; Block F (5 and 7 storeys with undercroft) comprises 124 apartments consisting of 57 one bedroom apartments, 61 two bedroom apartments and 6 three bedroom apartments; Block G (1, 2 and 4 storeys with undercroft) comprises 65 apartments consisting of 16 one bedroom apartments, 45 two bedroom apartments and 4 three bedroom apartments; Block H (4 storeys with undercroft) comprises 61 apartments consisting of 16 one bedroom apartments and 45 two bedroom apartments; Mixed use development comprising, commercial office development in Block C of 6 storeys with parapet above to 7 storey equivalent on elevations (c. 4,516sq.m), 1 retail unit at ground floor of Block B (c.147.5sq. m) and 3 retail units at ground floor of Block E as follows (c.106.2sq.m, c.141.6sq.m and c.492.2sq.m respectively) as well as a creche (c. 609sq. m) at ground floor and first floor of Block A; Vehicular access will be from the permitted Clonburris Southern Link Street (SDZ20A/0021) and R 113 to the east; Public Open Space/landscaping of c. 0.52 hectares (urban square) and linear open space (0.72 hectares) as well as a series of communal open spaces to serve apartments over undercroft level (and internal communal open space c. 685 sq.m; The development will also provide for all associated works and infrastructure to facilitate the development to include all ancillary site development works including footpaths, landscaping boundary treatments, public, private open space areas, car parking (396 no. spaces in a mixture of undercroft spaces Block A, Block B&D and Block E&F) and bicycle parking (1,232 spaces at undercroft and surface levels), single storey ESB substations/bike/bin stores, green roofs, solar panels at roof level of apartments, plant areas within blocks and all ancillary site development/construction works; Permission is also sought for connection to water supply, and provision of foul drainage infrastructure. This application is being made in accordance with the Clonburris Strategic Development Zone Planning Scheme 2019 and relates to a proposed development within the Clonburris Strategic Development Planning Scheme Area ' as defined by Statutory Instrument No. 604 of 2015; An Environmental Impact Assessment Report accompanies this planning application.
- Location
- Dublin 22, Co. Dublin Map
- Council
- South Dublin County Council
- Planning reference
- SDZ22A/0018
Numbers and dates
- Project type
- Mixed use
- Received
- 6 Oct 2023
- Granted
- 31 Oct 2023
- Site start notified
- 19 Dec 2023
Timeline
- Application received
- Granted
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file SDZ22A/0018 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 19 Dec 2023Notice filed · phase 1 · Block E & F shall be a six/seven-storey (respectively) residential development. Block E...View the site start
- 12 Feb 2024Notice filed · phase 2 · Block G shall be a Four storey apartment block consisting of ground plus three floors...View the site start
- 12 Feb 2024Notice filed · phase 3 · Block H shall be a four-story apartment block consisting of ground plus three floors...View the site start
- 11 Mar 2024Notice filed · phase 4 · Block A shall be a part 4 part 6 mixed use development, comprising of ground plus five...View the site start
- 7 May 2024Notice filed · phase 5 · Block B & D shall be a part 6 part 7 storey mixed use development, comprising of ground...View the site start
- 13 Jan 2025Notice filed · phase 6 · Block C shall be a 6-storey office block, comprising of ground plus five, containing 2no...View the site start
- Completion certificate recordedRecorded in Dec 2023 · 229 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Feb 2024 · 65 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Feb 2024 · 61 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area