Small residential · Co. Dublin

Amendments to the internal layouts and dwelling mix of permitted…, South-West Of Lucan, Co. Dublin

Granted 1 Jul 2026

Get updates on this application

We'll email you when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application SDZ26A/0009W at South-West Of Lucan, Co. Dublin: Amendments to the internal layouts and dwelling mix of permitted…
  • It was received by South Dublin County Council on 4 Jun 2026.
  • Status: Granted 1 Jul 2026.
  • Permission was granted on 1 Jul 2026 and no site start has been filed yet. The next step is a commencement notice, filed before building work begins; the start date and who will build it are not known yet.

Source: the South Dublin County Council planning register, checked 17 Jul 2026. Open the council's file

More planning applications in South-West Of Lucan · Planning applications in Co. Dublin

What and where

Amendments to the internal layouts and dwelling mix of permitted…

The proposed development will principally consist of amendments to the internal layouts and dwelling mix of permitted Blocks 1, 2, 3, 5, 8 and 9 to increase the total number of dwellings by 47 No. from 877 No. to 924 No. The amended dwelling mix increases studio units by 52 No., increases 1-bed units by 72 No., results in no change to 2-bed (3-person) units, decreases the 2-bed (4-person) units by 77 No. and results in no change to 3-bed units. Overall, the amendments will result in the following dwelling mix across all 9 No. permitted blocks: 97 No. studio units, 460 No. 1-bed units, 86 No. 2-bed (3-person) units, 240 No. 2-bed (4-person) units and 41 No. 3-bed units. To facilitate these amendments to the dwelling mix, amendments are also proposed: to the elevations and fenestration of Blocks 1, 2, 3, 5, 8 and 9; to increase cycle parking; and to public open spaces, communal amenity spaces and private amenity spaces (including balconies and terraces). As a result of these amendments, the overall gross floor area of the development will reduce by 112 sq m from 77,564 sq m to 77,452 sq m (including podium/undercroft car park area of 5,443 sq m).

Location
South-West Of Lucan, Co. Dublin Map
Planning reference
SDZ26A/0009W

Numbers and dates

Project type
Small residential
Received
4 Jun 2026
Granted
1 Jul 2026

Timeline

  1. Application received
  2. Granted

Outlook

What happens next

Permission was granted on 1 Jul 2026 and no site start has been filed yet. The next step is a commencement notice, filed before building work begins; the start date and who will build it are not known yet.

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file SDZ26A/0009W on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file

Reviewed build intelligence

What the documents establish

Government document review

Final grant records a 47-home increase within the existing Phase 2 permission, from 877 to 924 homes. The amendment does not add 924 new homes to its parent.

2 official documents inspected · Checked 2026-09-07 · Official file index

Final grant changes the parent mix by 47 homes

Granted amendment to Adamstown Phase 2

What the evidence says
The 11 August final grant modifies Blocks 1, 2, 3, 5, 8 and 9 of SDZ25A/0013W. The nine-block total changes from 877 to 924 homes; the additional scope is 47 homes. Gross floor area reduces from 77,564 to 77,452 m², including 5,443 m² of podium/undercroft parking. Parent conditions and expiry continue except where modified.

Why it may matter — interpretation
Estimators should price the changed internal layouts, facades and associated spaces against the parent design without duplicating the entire development.

What is not established
Commencement of this amendment and completion of the parent are not established.

Inspect the evidence

Final grant of amendment permission · p.1
increase the total number of dwellings by 47 · Issued 2026-08-11 · Final Grant Order 0740; decision 1 July 2026 · Checked 2026-09-07

increase the total number of dwellings by 47

Final grant of amendment permission · p.2
Alteration of a Previous Permission · Issued 2026-08-11 · Final Grant Order 0740; decision 1 July 2026 · Checked 2026-09-07

Alteration of a Previous Permission

The FI response retains 353 parking spaces

June FI parking explanation, subject to final-grant condition 3

What the evidence says
The June technical note retains 353 parking spaces. Its stated ratio changes from 0.40 to 0.38 spaces per home because the home count rises to 924, rather than because parking spaces are removed. The final grant still requires an agreed detailed parking strategy.

Why it may matter — interpretation
Parking managers and civil designers need the unchanged physical parking supply and revised allocation assumptions together.

What is not established
The note contains a neighbouring park reference in its introduction; final grant condition 2 controls the parent identity. Installed parking and management arrangements are unverified.

Inspect the evidence

AtkinsRealis parking technical note and management plans · p.2
353 no. car parking spaces · Issued 2026-06-04 · Technical note header 3 June; document history final revision 2 dated 4 June; received 4 June; selected introductory pages only · Checked 2026-09-07

353 no. car parking spaces

Final grant of amendment permission · p.2
Car Parking Strategy Plan · Issued 2026-08-11 · Final Grant Order 0740; decision 1 July 2026 · Checked 2026-09-07

Car Parking Strategy Plan

EV quantities and management require agreement before work

Pre-commencement condition on the amendment

What the evidence says
Condition 3 requires a parking strategy before development starts, including car sharing, allocation and enforcement, the number of charging bays, charging-hub installation and day-to-day EV management. The grant does not fix a charger make or quantity.

Why it may matter — interpretation
Electrical suppliers and parking operators need the agreed strategy before treating an EV specification as settled.

What is not established
An agreed compliance submission, charger selection or equipment order is not established.

Inspect the evidence

Final grant of amendment permission · p.2
Car Parking Strategy Plan · Issued 2026-08-11 · Final Grant Order 0740; decision 1 July 2026 · Checked 2026-09-07

Car Parking Strategy Plan

Occupation depends on the preceding infrastructure phase

Phasing condition for the additional 47 homes

What the evidence says
Condition 4 requires a detailed phasing schedule before commencement and council agreement to the work sequence. Blocks should generally be completed in full within one construction phase; occupation depends on the required facilities and infrastructure in the previous phase being complete to the council’s satisfaction.

Why it may matter — interpretation
Civil and building programmes need to coordinate the residential sequence with infrastructure delivery.

What is not established
No approved phasing schedule or satisfaction of the occupation condition was reviewed.

Inspect the evidence

Final grant of amendment permission · p.2
Phasing. · Issued 2026-08-11 · Final Grant Order 0740; decision 1 July 2026 · Checked 2026-09-07

Phasing.
Remaining document questions
  • Has the council agreed the amendment-specific parking strategy and phasing schedule?

The declared pages of these government-published PDFs were visually inspected. Other catalogue files, later compliance, procurement and installed specifications were not established. Historical weekly membership is retained separately from these document dates.

How we know this

From the South Dublin County Council planning register, checked 17 Jul 2026. We link to the council's own file so you can check the official record before you act. Facts from the planning documents were read from the documents in that file.

Explore the area

More planning activity near South-West Of Lucan

Get alerts for South-West Of LucanFree. We email you when new applications appear.

Free email alerts

Get new South-West Of Lucan projects by email

New applications, decisions and site starts in South-West Of Lucan, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options