Large residential · Co. Dublin
Site at the corner of Airton Road and Belgard Road, Tallaght, Dublin 24, D24 HD35
Granted 20 Feb 2020
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 24 by email
Key facts
- Planning application SHD3ABP-305763-19 at Site At The Corner of Airton Road and Belgard Road, Tallaght, Dublin 24, D24 HD35: 328 homes.
- It was received by South Dublin County Council on 25 Oct 2019.
- Status: Granted 20 Feb 2020.
Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Dublin 24 · Planning applications in Co. Dublin
Council register
The council's register shows: Decision to grant on 20 Feb 2020.
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
328 homes
Demolition of the existing industrial buildings on site (4,800sq.m) and the construction of 2 blocks comprising: 328 apartments (93 1-bed, 222 2-bed and 13 3-bed), ancillary residential support facilities and commercial floorspace measuring 31,147sq.m gross floor space above a single basement level measuring 5,861sq.m. Block A is a part-5 to part-7 storey (13,710sq.m) over basement block comprising 149 apartments with office space (222sq.m). Block B is a part-6 to part-9 storey (17,437sq.m) over basement block comprising 179 apartments, 2 double-height retail/commercial (Class 1/Class 2) units (354sq.m), a café/restaurant (313sq.m), a creche (360sq.m), internal residents amenity area (644sq.m) at ground floor including reception (37.7sq.m), residents lounge (91.3sq.m), private dining area (52.6sq.m), co-working space (45.5sq.m), games room (47.3sq.m), gym (80sq.m) and communal lounge (220sq.m) at 6th floor level. The development also consists of the provision of a landscaped courtyard; public plaza at the corner of Airton and Belgard Road; pedestrian access from Airton Road to the Technological University campus; balconies; landscaped roof terrace at 6th floor level (7th Storey) of Block B (671sq.m); 184 car parking spaces at basement level including 14 club car spaces, 10 disabled parking spaces and 4 creche parking spaces; 727 basement and surface bicycle parking spaces; 4 motorbike parking spaces; bin storage; boundary treatments; green roofs; hard and soft landscaping; plant; lighting; Vodafone cabin sub-station; ESB sub-stations, switch rooms and generators; and all other associated site works above and below ground.
- Location
- Dublin 24, Co. Dublin Map
- Council
- South Dublin County Council
- Planning reference
- SHD3ABP-305763-19
Numbers and dates
- Homes
- 328
- Floor area
- 37,008 m²
- Estimated construction value
- €74m to €97mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Large residential
- Received
- 25 Oct 2019
- Granted
- 20 Feb 2020
- Site start notified
- 21 Jun 2022
Timeline
- Application received
- Granted
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file SHD3ABP-305763-19 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 21 Jun 2022Notice filed · Construction of two new apartment blocks (Block A & B), at Junction of Airton Rd &...View the site start
- Completion certificate recordedRecorded in Jun 2022 · 328 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.