  • Planning application SHD3ABP-306705-20 at Dublin 24, Co. Dublin: Demolition of existing factory/warehouse buildings.
  • It was received by South Dublin County Council on 19 Feb 2020.
  • Status: Granted 16 Jun 2020.

Source: the South Dublin County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Dublin 24 · Planning applications in Co. Dublin

Council register

The council's register shows: Decision to grant on 16 Jun 2020.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Demolition of existing factory/warehouse buildings

Demolition of existing factory/warehouse buildings on site (total floor area c. 10,076.8sq.m). Construction of 502 apartments (comprising 197 1-bed; 257 2-bed; and 48 3-bed units) within 6 blocks ranging in height from 4 to 8 storeys. All residential units provided with associated private balconies/terraces to the north/south/east/west elevations. Provision of residential amenity facilities, 3 retail units, creche and services/bin store areas (total non-residential floor area c.1,839sq.m). A total of 202 car parking spaces (at basement and undercroft levels) and 584 no. bicycle parking spaces. Vehicular/pedestrian/cyclist accesses from Greenhills Road and Airton Road. Provision of road improvements and pedestrian crossings. All associated site development works, open space, landscaping, boundary treatments, plant areas, pv panels (at roof level), waste management areas, and services provision (including ESB substations).

Location
Dublin 24, Co. Dublin Map
Planning reference
SHD3ABP-306705-20

Numbers and dates

Project type
Large residential
Received
19 Feb 2020
Granted
16 Jun 2020
Site start notified
10 Aug 2022

Timeline

  1. Application received
  2. Granted
  3. Site start notified

Outlook

What happens next

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description
  • Crèche or childcare facilityNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file SHD3ABP-306705-20 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file

How we know this

From the South Dublin County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 10 Aug 2022Notice filed · phase 1 · A residential development ranging from 6-8 stories with 502 apartments split over 3...View the site start
  2. 27 Sep 2023Notice filed · phase 2 · Construction of a residential development on the site of the now vacant Gallagher’s...View the site start
  3. 20 Dec 2023Notice filed · phase 3 · Construction of a residential development on the site of the now vacant Gallagher’s...View the site start
  4. 18 Nov 2025Notice filed · phase 4 · Development of Residential Amenity Facilities only at the Ground and First Floor of...View the site start
  5. 18 Nov 2025Notice filed · phase 5 · Development of Residential Amenity Facilities only at the Ground Floor of Block D...View the site start
  6. 18 Nov 2025Notice filed · phase 6 · Development of Creche Facilities only at the Ground Floor of Block C, Airton Road. A new...View the site start
  7. Completion certificate recordedRecorded in Aug 2022 · 107 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
  8. Completion certificate recordedRecorded in Sep 2023 · 275 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
  9. Completion certificate recordedRecorded in Dec 2023 · 120 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 24

Get alerts for Dublin 24Free. We email you when new applications appear.

Free email alerts

Get new Dublin 24 projects by email

New applications, decisions and site starts in Dublin 24, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options