Commercial new build · Co. Dublin
22. The development shall comply with the following requirements of…, Co. Dublin
Decision due 8 Dec 2026
Key facts
- Planning application WEB2006/26Sub05 at Co. Dublin: The development shall comply with the following requirements…
- The applicant is Stormborn Capital Acquisition Three Ltd. The agent is McOrm.
- It was received by Dublin City Council on 15 Oct 2026.
- Status: Decision due 8 Dec 2026.
- The council's decision is due on 8 Dec 2026. Building work can only follow a grant of permission.
Source: the Dublin City Council planning register, checked 25 Oct 2026. Open the council's file
More planning applications in And Immediately Adjacent Lands. The Site Is Bound · Planning applications in Co. Dublin
What and where
22. The development shall comply with the following requirements of…
22. The development shall comply with the following requirements of Transport Planning Division of Dublin City Council: e. Prior to commencement of development, and on appointment of a contractor, a Construction Management Plan for the demolition and construction phase of the development shall be submitted to the planning authority for written agreement. This plan shall provide details of intended construction practice for the entire development and at each phase, including a detailed traffic management plan, hours of working, noise management measures, off-site disposal of construction waste and access arrangements for labour, plant and materials, including location of plant and machine compound. The appointed contractor shall liaise with Dublin City Council Road Works Control Division and National Transport Authority / appointed contractor constructing BusConnects during construction period.
- Location
- Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- WEB2006/26Sub05
- Agent
- McOrm
Numbers and dates
- Project type
- Commercial new build
- Received
- 15 Oct 2026
- Decision due
- 8 Dec 2026
Site history
This site's history
-
Application WEB2006/26Sub04 at the same address: received 14 Oct 2026, no decision recorded yet.
25. a. Prior to the commencement of any works, a Construction and Demolition Waste Management Plan must be furnished to and approved by… Same address -
Application WEB2006/26Sub03 at the same address: received 6 Oct 2026, no decision recorded yet.
13. Prior to commencement of demolition works the applicant shall clarify for the written agreement of the Planning Authority details of… Same address -
Application WEB2006/26Sub02 at the same address: received 6 Oct 2026, no decision recorded yet.
c) Biodiversity Mitigation, Monitoring & Enhancement Biodiversity mitigation and monitoring shall be carried out in accordance with the… Same address
Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file WEB2006/26Sub05 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Dublin City Council planning register, checked 25 Oct 2026. We link to the council's own file so you can check the official record before you act.
Explore the area