Infrastructure, No. 2 Branch Road North Extension, Dublin Port, Dublin 3 - Planning Application WEB2056/26
Dublin / Dublin 3 / No. 2 Branch Road North Extension, Dublin Port, Dublin 3
Source-linked planning record
Infrastructure, No. 2 Branch Road North Extension, Dublin Port, Dublin 3 - Planning Application WEB2056/26
Dublin / Dublin 3 / No. 2 Branch Road North Extension, Dublin Port, Dublin 3- PB ref
- PB--3297069870
- Plan ref
- WEB2056/26
- Authority
- Dublin City Council
- Stage / date
- Further Information / 25 Jun 2026
- Est. value band
- Value not disclosed
- Project class
- Infrastructure
- Promoter
- not available yet
- Architect / agent
- not available yet
Key facts
Lead summary
- Source
- Dublin City Council public planning register
- Planning authority
- Dublin City Council
- Application reference
- WEB2056/26
- Applicant
- not available yet
- Agent
- not available yet
- Decision stage
- Further Information
- Decision due
- 25 Jun 2026
Official description
Verbatim source text
The development consists of constructing a pipe bridge with an approximate overall height of 8m with associated concrete supports, to allow new pipelines and cables to be routed between two yards. This pipe bridge will span between the Circle K Terminal, and the pipe track on the opposite side of 2 Branch Road North Ext., outside TOP Yard 1, located in Dublin Port. Signs informing of the clearance height beneath the pipe bridge will also be installed on the bridge. A height restriction barrier with an accompanying sign informing of the clearance space beneath the pipe bridge will be installed over 2 Branch Road North Extension, south of the pipe bridge.
Verify against official sourceProject team
Named source parties
- Promoter
- not available yet
- Planning agent
- not available yet
Lifecycle timeline
Application to site progress
-
Applied
1 May 2026 WEB2056/26 -
Decision
Grant Permission 25 Jun 2026 -
Commenced
No commencement indexed Owner-export and BCMS records are indexed only when a reliable source link exists. -
Completed
Completion not recorded Smaller works often do not require a completion certificate.
Likely trades & supplier leads