Planning record · Co. Dublin
A site within the Royal Dublin Society, RDS Grounds, Dublin 4
Granted 8 Nov 2024 (final grant issued 16 Dec 2024)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 4 by email
Key facts
- Planning application WEB2142/24 at A Site Within The Royal Dublin Society, RDS Grounds, Dublin 4: Amendments to the new Anglesea Stand.
- It was received by Dublin City Council on 17 Sep 2024.
- Status: Granted 8 Nov 2024 (final grant issued 16 Dec 2024).
- Work was due to start on 26 Aug 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Dublin City Council planning register, as last seen on 5 Oct 2026. Search the council's register
More planning applications in Dublin 4 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 8 Nov 2024.
Search the Dublin City planning register
Application details as we last saw them in the national register on 5 Oct 2026.
What and where
Amendments to the new Anglesea Stand
PROTECTED STRUCTURE: For development at a site within the Royal Dublin Society (RDS) Grounds, Ballsbridge, Dublin 4. The development will consist of amendments to the new Anglesea Stand, permitted under register reference 3937/23. The proposed amendments to the permitted stand include: a) minor alterations to the internal arrangement including relocation of lift cores; rearrangement of plantrooms, stores, WCs and bars; omission of internal event space corridors; addition of a flexible servery space at Level 02; and; cross bracing structures within the stand. b) alterations to the external elevations to include an increase in the overall height to c.24.04m (c.2.74m increase); alterations of signage zones including an increase of c.7sq.m on the north elevation of the new stand; provision of 2 no. roof maintenance access platforms; and; provision of 2 no. additional pitch access points from the lower tier seating and reduction of vomitory widths. c) amendments to the permitted finishes including omission of glazing at Level 1, and part replacement of render with precast concrete at Level 0. d) increase in total capacity of the stand to 6,844 (69 no. additional spectators). There is no increase in the overall footprint of the permitted new stand.The proposed development will also include relocation of the permitted substation east of existing South Stand and its construction (c.29sq.m in area and c.4.3m in height) at the western site boundary; and; relocation of a generator to the eastern boundary of the site.
- Location
- Dublin 4, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- WEB2142/24
Numbers and dates
- Project type
- Planning record
- Received
- 17 Sep 2024
- Decision to grant
- 8 Nov 2024
- Final grant
- 16 Dec 2024
- Site start notified
- 26 Aug 2026
- Protected structure
- Yes
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Site history
This site's history
-
Earlier permission 3937/23 for this site: granted 4 Aug 2023, commencement notice filed for a start on 21 Oct 2024.
PROTECTED STRUCTURE: The development will consist of the redevelopment of the Anglesea Stand to provide a new 3 level grandstand (6,775… Named in this application's description
Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference WEB2142/24.Search the register
How we know this
From the Dublin City Council planning register, as last seen on 5 Oct 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 26 Aug 2026Notice filed · Construction of 2 new standing terraces on the east and west sides of the completed...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.