House extension · Co. Dublin
Poolbeg AGI, Poolbeg Power Station, Pigeon House Road, Dublin 4
Granted 27 Aug 2025 (final grant issued 1 Oct 2025)
Key facts
- Planning application WEB2574/25 at Poolbeg AGI, Poolbeg Power Station, Pigeon House Road, Dublin 4: 1 no. gas analyser kiosk.
- It was received by Dublin City Council on 3 Jul 2025.
- Status: Granted 27 Aug 2025 (final grant issued 1 Oct 2025).
- Work was due to start on 6 Apr 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Dublin City Council planning register, checked 2 Jun 2026. Search the council's register
More planning applications in Dublin 4 · Planning applications in Co. Dublin
What and where
1 no. gas analyser kiosk
The development will consist of 1 no. gas analyser kiosk, minor road extension, rooftop-mounted solar panels, modification to the entrance gate and all ancillary services and associated site work. Part of the works will include decommissioning and removal of existing PRS building, Water Baths Heaters and associated pipework.
- Location
- Dublin 4, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- WEB2574/25
Numbers and dates
- Project type
- House extension
- Received
- 3 Jul 2025
- Decision to grant
- 27 Aug 2025
- Final grant
- 1 Oct 2025
- Site start notified
- 6 Apr 2026
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference WEB2574/25.Search the register
How we know this
From the Dublin City Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.
Site starts
Commencement notices for this permission
- 6 Apr 2026Notice filed · The development will consist of 1 no. gas analyser kiosk, minor road extension, rooftop...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.