Site start · Co. Dublin
Partially commenced, Co. Dublin
Site start 8 Jan 2021
Key facts
- Site start record at Co. Dublin: Partially commenced.
- The planning authority is Dublin City Council.
- Status: Site start 8 Jan 2021.
Source: the Dublin City Council planning register, checked 9 Jul 2026. Search the council's register
What and where
Partially commenced
Partially commenced: 54 of 64 permitted units have commencement evidence; 10 remaining units expected. The proposed development will consist of the construction of a ‘Build to Rent’ residential development comprising of 69 no. apartments (51 no. 1 beds, 18 no. 2
- Location
- Co. Dublin Map
- Council
- Dublin City Council
- Application type
- Permission
- Agent named on the notice
- Not Indexed
Numbers and dates
- Estimated construction value
- €2.2m to €3.1mOur estimate from stated homes and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Small multi-unit
- Site start
- 8 Jan 2021
Documents and evidence
Check the record
- Council planning registerSearch the register on planning.agileapplications.ie.Search the register
- Homes permitted and started64 permitted · 54 commenced · 10 remaining (reviewed reconciliation)Download supplier brief
How we know this
From the Dublin City Council planning register, checked 9 Jul 2026. We link to the council's own file so you can check the official record before you act.