Site start · Co. Galway
Clifden, Galway
Granted 13 Nov 2023 (final grant issued 8 Jan 2024)
Key facts
- Site start record 2360160 at Clifden, Co. Galway: Residential development.
- The planning authority is Galway County Council.
- Status: Granted 13 Nov 2023 (final grant issued 8 Jan 2024).
Source: the Galway County Council planning register, as last seen on 10 Jun 2026. Open the council's file
More planning applications in Clifden · Planning applications in Co. Galway
Council register
The council's register shows: Granted on 13 Nov 2023.
Search the Galway planning register
Application details as we last saw them in the national register on 10 Jun 2026.
What and where
Residential development
Commencement Notice for 30 no. residential units, comprised of: 5no. three-bed units (two storey); 8no. one-bed units (single storey/ground floor); 3no. two-bed units (single storey); & 14no. two bed duplex units; the provision of 47no. car parking spaces, including 3no. accessible spaces & 10no. EV charging spaces; the provision of 36no. onsite bicycle parking spaces; the provision of footpaths & pedestrian crossings to facilitate connections to the existing public footpath network. The proposed development includes for site landscaping, public service connections & all other associated site development works necessary to facilitate the proposed development. Gross floor space of proposed works 2,336.8 m²
Description as published by the council. Its text starts part-way through a sentence.
- Location
- Clifden, Co. Galway Map
- Council
- Galway County Council
- Planning reference
- 2360160
- Application type
- Commencement Notice
- Owner named on the notice
- Conroy Contractors
- Agent named on the notice
- Conroy Contractors
Numbers and dates
- Project type
- Small residential
- Received
- 23 Feb 2023
- Decision to grant
- 13 Nov 2023
- Final grant
- 8 Jan 2024
- Site start notified
- 24 Sep 2024
Documents and evidence
Check the record
- Council planning fileThe application file 2360160 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Galway County Council planning register, as last seen on 10 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 24 Sep 2024Notice filed · phase 1 · Construction of 3 no. 3 bed Terrace houses and all associated site worksView the site start
- 30 Sep 2024Notice filed · phase 2 · Construction of a residential development - Block A1 units 4-9 - 6 units- 2 no. 3 bed...View the site start
- Completion certificate recordedRecorded in Sep 2024 · 3 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Sep 2024 · 6 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Sep 2024 · 12 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.