Final grant covers the centre and its heat network
Granted energy-centre and pipeline scope
What the evidence says
The 10 August final grant covers a district-heating energy centre of 1,439.1 m², demolition of 1,290 m² and approximately 7,877 m of district-heating network pipeline. Condition 2 gives ten years for the permitted development. Condition 3 requires an agreed phased consultation, coordination and monitoring regime before pipeline works commence.
Why it may matter — interpretation
Building and civil teams should separate the centre works from the network delivery programme and its coordination requirements.
What is not established
No pipeline start, building completion, commissioning or equipment award was established.
Inspect the evidence
Final grant and conditions · p.1
7,877m · Issued 2026-08-10 · Chief Executive Order PL.26.0672; final grant 10 August · Checked 2026-09-07
7,877m
Final grant and conditions · p.2
ten [10] years · Issued 2026-08-10 · Chief Executive Order PL.26.0672; final grant 10 August · Checked 2026-09-07
ten [10] years
Final grant and conditions · p.2
phased regime · Issued 2026-08-10 · Chief Executive Order PL.26.0672; final grant 10 August · Checked 2026-09-07
phased regime